CXO 10.0% 11.0¢ core lithium ltd

Ann: Quarterly Activities and Cashflow Report 31 December 2022, page-83

  1. 2,781 Posts.
    lightbulb Created with Sketch. 6065
    Unless I've missed it, no-one has commented that A$3.3m was reported as Production operating costs. Presumably this is the cost of producing the Ore for DMS stockpiles and the DSO shipment that will soon be A$20m of cash. Now that's a nice profit margin!!.

    On the negative, the cumulative PP&E and other non-current asset expenditure is getting above the totals I'd expected. If there is a $10's of millions capital overrun, its a couple of cents negative to the share price. The big boy's will have known this as they unpacked the quarterly. With Core having raised $100m, this won't cascade to a capital raise but it may have been a problem if Core hadn't raised the extra $100m.

    The table below is the combination of the last six quarterlies. Up until the September quarter, costs were still under the known budget of A$95m, but not by much ($95m = $89m + $6m extra for DMS acceleration). This quarter had $51.5m of Capex including $41m of other non-current assets - Mine Development. This takes the known Mine development to $54.7m and if the other non-current asset expenditure was also mine development, the cost of this component is now out at $75m. This is slightly over double the quoted $33.9m for Grants pre-strip.

    Interestingly Core has decided not to front-foot this in the quarterly and explain what's happening, particularly since the pre-strip appeared to be complete very early in the December quarter:
    • Is there just a massive cost blow-out and the extra charges were agreed in the December quarter, hopefully to be forgotten or forgiven when the spod shipments start?
    • Have some expensive costs towards BP33 been incurred?
    • Is this starting to capture the $10.3m of FY23 expenditure in the DFS for processing and other infrastructure?
    • Has Core implemented some other project like connecting the remaining 8km to the grid? (and if so, why not announce it?)
    • Is a useful amount of capital expenditure being spent to recover lithium from fines (or prepare for DSO sales)?

    https://hotcopper.com.au/data/attachments/5017/5017248-b1faf65991977448b3b583cbb1aaef6b.jpg

    The August 2021 estimated cost was A$89m. The A$100m capital raise noted A$6m extra for DMS project acceleration taking the total to A$95m.
    https://hotcopper.com.au/data/attachments/5017/5017170-ea5be0725584782ecc095a67e9380548.jpg
    https://hotcopper.com.au/data/attachments/5017/5017240-8c3011e0be61c36fa9aedc20d282315c.jpg
 
watchlist Created with Sketch. Add CXO (ASX) to my watchlist
(20min delay)
Last
11.0¢
Change
0.010(10.0%)
Mkt cap ! $235.0M
Open High Low Value Volume
10.5¢ 11.5¢ 10.0¢ $3.029M 27.71M

Buyers (Bids)

No. Vol. Price($)
7 374502 11.0¢
 

Sellers (Offers)

Price($) Vol. No.
11.5¢ 3715512 56
View Market Depth
Last trade - 16.10pm 12/07/2024 (20 minute delay) ?
CXO (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.