We don't know how much HM is in the HMC, so we can't even guess at recoveries. 95% HM in HMC is design, but it might be 85% and the rest silicates.
The obvious commissioning concern is WCP throughput while hitting plant design availability and recoveries, as per Qtrly
They started commissioning 2 Nov and declared commercial production 18 Nov (meaning everything is running close to design at commercial rates). At 23.4Mtpa mining rate through the WPC, over 1.5 months to Dec 31st, 3Mt would be mined through the WPC, but they only ran through 1Mt...
That looks very low considering commercial production was declared mid November
- Forums
- ASX - By Stock
- Ann: Quarterly Activities and Cashflow Report
We don't know how much HM is in the HMC, so we can't even guess...
-
- There are more pages in this discussion • 42 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add STA (ASX) to my watchlist
(20min delay)
|
|||||
Last
9.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $138.9M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
STA (ASX) Chart |
Day chart unavailable
The Watchlist
LPM
LITHIUM PLUS MINERALS LTD.
Simon Kidston, Non--Executive Director
Simon Kidston
Non--Executive Director
SPONSORED BY The Market Online