    Utah Point Hub

    Ore mined increased quarter on quarter driven by the ramp up of operations at Wonmunna, progression through the
    north-western pit following the significant pre-strip undertaken in the prior quarter.
    Produced tonnes were in line with the prior quarter. Plant upgrades and modifications were undertaken across both Iron
    Valley and Wonmunna during the quarter to enable further flexibility to meet blending requirements.
    Shipped tonnes increased quarter on quarter due to the continued ramp up of Wonmunna’s operations.

    Utah Point Hub
    Wonmunna
    MRL completed a small program of diamond drilling at Wonmunna during the quarter. A total of 490m of PQ core was
    collected for the purpose of geo-metallurgical test work.

    With site capacity
    currently at 5 million tonnes per annum
    – with the potential to further expand
    output to 10 million tonnes per annum
    pending additional approvals and at little
    capital cost – Wonmunna demonstrates
    MRL’s capacity to identify and capitalise on
    new opportunities with agility and speed.


    ...

 