$1M per month @ $150 ph is 6,666 hours.
6,666 / 160 hours - 4 x 40 hour weeks is 41 people.
41 people working on this project.
41 Engineers?
Yet no estimate until mid next year.
If it is that number of engineers, it is a lot.
This is full scale detailed design, operations readiness technical writing, construction planning levels of people.
If that is not what the company is paying for, I'd agree, a full breakdown of the Engineering costs would be worth seeing.
- Forums
- ASX - By Stock
- Ann: Quarterly Activities/Appendix 5B Cash Flow Report
$1M per month @ $150 ph is 6,666 hours. 6,666 / 160 hours - 4 x...
-
-
- There are more pages in this discussion • 39 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add TVN (ASX) to my watchlist
|
|||||
Last
5.8¢ |
Change
-0.002(2.54%) |
Mkt cap ! $99.06M |
Open | High | Low | Value | Volume |
5.9¢ | 5.9¢ | 5.8¢ | $31.10K | 534.3K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
7 | 533721 | 5.7¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
5.8¢ | 104764 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
7 | 533721 | 0.057 |
4 | 501953 | 0.056 |
2 | 270000 | 0.055 |
2 | 143425 | 0.054 |
1 | 100000 | 0.052 |
Price($) | Vol. | No. |
---|---|---|
0.058 | 104764 | 2 |
0.059 | 42110 | 2 |
0.060 | 130168 | 2 |
0.062 | 309967 | 3 |
0.063 | 100000 | 1 |
Last trade - 15.33pm 11/07/2024 (20 minute delay) ? |
Featured News
TVN (ASX) Chart |