re: Ann: Quarterly Activities Report, Appendi... Thank you elpha.
You be sure to say hi to hal2000 for me also.
Is that from the horses mouth?
Hard to work out from the quarterly's - no where do they say in plain English "the initial 25 metres of the adit is virtually complete" and I don't understand why no pics - IDC are normally goods with their pics.
December Quarterly:
------------------------------------------------------------
Initial development of the portal, and the first 25-50 metres of development drive, will be followed by a larger underground development and drilling campaign over 775 metres
Planned drilling and portal development was temporarily halted during the Christmas-New Year period, to allow for the completion of the Landowner Investigation Study (LIS) on-site, as all accommodation on-site was utilised as part of the LIS.
------------------------------------------------------------
March Quarterly:
The Company had commenced the initial development of the high grade gold/silver zones, with the preparation of a portal for an underground development drive (adit).
Initial work has been delayed on the underground drive (adit) while the various finance discussions are underway.
------------------------------------------------------------
*Initial development*
*Planned drilling and portal development*
*commenced the initial development*
*preparation of a portal*
*Initial work has been delayed*
....all sounds very "initial" and "planned" but is it actually executed???
Would be a lot simpler to just say "we have COMPLETED 25 metres of the adit" wouldn't it?