Guidance was not provided because they want to be fully confident (and that should happen next month).
Production was down as per previous guidance
Increased production costs are a direct consequence of (2)
Borax is a nit in the overall scheme of things, however production is increasing, and profitability should improve with the devaluation of the Argentine peso in any case
Phase 2 planning is not dependent on nameplate, and is continuing. Phase 2 is dependent on resolving the pond issue, but is not dependent on the purification circuit issues (though these seem to be solved) since Phase 2 will only include the primary circuit which has been performing well above specification
Japan project seems to be progressing fine as far as I can see. It is dependent on Olaroz Stage 2 in any case so there is no immediate time constraint as farr as designing and building the plane