QUARTERLY ACTIVITIES REPORT December 2017
■ Construction activities at the Altura Lithium Project at Pilgangoora continued during the quarter, and are nearing completion
■ Project commissioning remains on schedule for Q1 2018
■ First lithium concentrate sales remain on schedule for Q2 2018
■ Altura set to become the first major hard-rock producer in 2018
■ Definitive Feasibility Study for Stage 2 expansion of the Project targeted for completion in April 2018
■ Upgraded JORC Ore Reserve and Mineral Resource estimates, including significant portions in the Proved and Measured categories
■ Southern Ridge Deposit at Pilgangoora, which displays significant potential, to be infill drilled to improve the Project’s reserve and resource estimates
■ Regional exploration program of Altura’s other Pilbara tenements to be undertaken
- Forums
- ASX - By Stock
- Ann: Quarterly Activities Report
QUARTERLY ACTIVITIES REPORT December 2017 ■ Construction...
-
- There are more pages in this discussion • 31 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add 1MC (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.6¢ |
Change
0.004(12.5%) |
Mkt cap ! $8.897M |
Open | High | Low | Value | Volume |
3.2¢ | 3.6¢ | 3.2¢ | $23.23K | 677.2K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
4 | 119319 | 3.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.6¢ | 58388 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
4 | 119319 | 0.032 |
3 | 56920 | 0.031 |
2 | 28366 | 0.030 |
1 | 19200 | 0.029 |
1 | 35749 | 0.027 |
Price($) | Vol. | No. |
---|---|---|
0.036 | 58388 | 1 |
0.037 | 65000 | 1 |
0.038 | 75000 | 1 |
0.039 | 70000 | 1 |
0.040 | 18500 | 1 |
Last trade - 15.59pm 16/08/2024 (20 minute delay) ? |
Featured News
1MC (ASX) Chart |