    A good activities report with an estimate on some key milestones :
    "Following completion of the 2020 drill program, an interim update to the overall Elan Project resource is
    on track for completion in 4Q 2020.
    The Elan Project PFS remains on track for completion by mid-2021."

    Plus there is an indication of the continued work program over the winter months:
    "Large-scale carbonisation tests (+500kg moveable wall oven) are also set
    to be conducted over coming months. Hydrogeological studies, First Nations and other stakeholder
    consultation, and environmental baseline sampling remains ongoing."

    IMOHO, this project is progressing as well as can ever be expected in this social media world and the resource also looks first class - IMO again.
 