The construction of the Kimberlite Bulk Sampling Plant (“KBSP”) has progressed well during the Quarter,
despite logistical and customs clearance challenges, and is moving towards being commissioned shortly.
Kimberlite samples continue to be accumulated at the KBSP stockpile for processing. On average, the KBSP will
process approximately two bulk samples every six weeks once fully operational.
Compare to the Q1 report:
The balance of the KBSP equipment has been trial erected at the manufacturers in Johannesburg, South Africa
and major components already en-route. Due to global logistics challenges, the plant is expected to be
commissioned towards the end of the second quarter. This should not hamper/ delay the program as the
crushing section is complete and will continue to reduce the kimberlite samples down to the required -18mm
particle size which can then be treated through the alluvial main treatment plant as required until the KBSP is
complete.
- Forums
- ASX - By Stock
- LOM
- Ann: Quarterly Activities Report
Ann: Quarterly Activities Report, page-12
Featured News
Add LOM (ASX) to my watchlist
(20min delay)
|
|||||
Last
4.1¢ |
Change
0.001(2.50%) |
Mkt cap ! $11.89M |
Open | High | Low | Value | Volume |
4.1¢ | 4.1¢ | 4.0¢ | $728 | 18.07K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 1425 | 4.1¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
4.2¢ | 3000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 1425 | 0.041 |
1 | 42672 | 0.040 |
1 | 77958 | 0.039 |
1 | 45446 | 0.038 |
1 | 100000 | 0.037 |
Price($) | Vol. | No. |
---|---|---|
0.042 | 3000 | 1 |
0.043 | 220000 | 1 |
0.045 | 20000 | 1 |
0.046 | 145000 | 1 |
0.048 | 50000 | 1 |
Last trade - 15.54pm 13/11/2024 (20 minute delay) ? |
Featured News
LOM (ASX) Chart |