WWI 13.3% 1.7¢ west wits mining limited

Ann: Quarterly Activity Report, page-2

  1. 964 Posts.
    lightbulb Created with Sketch. 311
    Quarterly Activity Report – June 2021
    Reporting Period 1
    st April – 30
    th June 2021
    HIGHLIGHTS
    • Steps taken by WWI’s Corporate Affairs and legal consultants during the reporting period were
    critical to the granting of the mining right (“MR”) by the Department of Mineral Resources &
    Energy (“DMRE”) in July 20211
    (post-reporting period)
    • 2,500m infill drilling program on the Kimberley East area of the Witwatersrand Basin Project
    (“WBP”) was successful in converting more of the existing JORC Mineral Resource Estimate
    (“MRE”) to Measured & Indicated categories2
    • 2.25Moz Au at 3.98g/t of the global MRE for the granted mining right area is now in
    Measured and Indicated categories (63%), being the precursor categories for possible
    conversion to Ore Reserves3
    • Independent Definitive Feasibility Study (“DFS”) on WBP’s first stage of development (Qala
    Shallows) significantly progressed during the period for scheduled completion in August
    2021
    West Wits Mining (ASX: WWI, ‘West Wits’ or ‘the Company’) is pleased to present its latest quarterly report for
    the period ending 30 June 2021.
    SOUTH AFRICA
    Witwatersrand Basin Project (“WBP”), Central Rand (WWI: 66%)
    Exploration
    West Wits commenced an infill drilling program in Nov-20, comprised of approximately 2,500m of diamond
    core and percussion drilling targeting the upper 300m that host the orebodies in the vicinity of the Qala Shaft
    area. The aim of the drilling program was to increase the Mineral Resource confidence in areas targeted for
    early mining to allow WWI to increase the capacity for declaration of ore reserves on completion of the DFS. A
    total of fourteen (14) new holes (mother holes and deflections) intersecting the K10, K9A, K9B, K8 and K7 reef
    bands were completed by three rigs. In addition, West Wits geologists re-logged the mineralised zones of
    three previously drilled MSA drillholes.
    The K9B results from the drilling program are the key driver in the grade increase of the Global MRE to 4.24g/t
    Au which is highlighted by the infill-drilling campaigns best result, hole RLKDD-44 with 1.68m @ 5.81g/t Au
    [123m], including 0.98m @ 9.07g/t (Figure 1)
    2
    .
    ASX Announcement and Media Release
    29 July 2021
    Figure 1: Planer view of the eastern portion of the Kimberley East Project which was the focus of the infill-drilling
    campaign at the Qala Shallows with reference to cross-sections depicted in Figure 2’s intersection
    results.
    Figure 2: Cross Section highlighting selected intersection results (grade and width) of drillholes RLKPDRE 22, 23,
    24, 39, 40, and 41 for the K9B, K9A and K8 Kimberley Reef conglomerates.
    The infill drill program successfully achieved its aim to upgrade a significant block of Indicated and Inferred
    MRE categories which are contained within the near to medium-term mine plan thereby enhancing confidence
    and our capacity to declare reserves2
    . Upgrading areas of the Inferred MRE is a critical step towards the
    Company being able to maximise the capacity for declaration of a maiden ore reserve for the Qala Shallows
    project upon completion of the DFS which is currently scheduled for completion in August 2021.
    The increase in the Measured MRE category provides a higher confidence level in the important early mining
    areas targeted for the Qala Shallows area. The updated 3D geological block model enables the mine
    engineering team to improve and optimise the mine plan which will enhance the development and financial
    model for project execution.
    The exploration results and updated resource modelling were released on 5th July 2021, soon after the end of
    the reporting period when the majority of the work was completed. The resource update covered the existing
    prospecting right (“PR”) at that time, increasing the global MRE to 32.78Mt @ 4.24g/t for 4.47Moz Au (2g/t cutoff)2
    . Upon granting of the mining right1
    the global MRE was subsequently restated to 25.91Mt @ 4.26g/t for
    3.55Moz Au (2g/t cut-off) on the 23rd July 20213
    (Table 1), allowing for the reduced mining right tenement
    footprint compared to the previous PR area.
    ASX Announcement and Media Release
    29 July 2021
    TABLE 1: UPDATED GLOBAL MRE FOR THE WITWATERSRAND BASIN PROJECT AT 2.0G/T CUT-OFF3
    MRE Category Tonnes (M) Grade (g/t Au) Ounces
    Measured 4.91 4.33 683,000
    Indicated 12.70 3.84 1,570,000
    Measured & Indicated 17.61 3.98 2,253,000
    Inferred 8.31 4.86 1,298,000
    Total 25.91 4.26 3,551,000
    Notes: Global MRE set at a 2.0g/t Au cut-off. Reported in accordance with the JORC Code of 2012.
    Number differences may occur due to rounding errors.
    The mining right footprint was constrained relative to the prospecting right area to minimise the impact of the
    mine on interested and affected parties. The areas not included in the reduced mining right area were non-core
    and do not affect the mine plan. The Company has lodged applications to re-secure certain sections of the old
    prospecting right area and thereby reintroduce additional resources to the MRE. The Company anticipates that,
    subject to the acceptance of the new prospecting right, a significant portion of the old resource would be
    recaptured.
    Previously, the K8 Reef was exploited mainly towards the west of Durban Roodepoort Deep (DRD). The K8 is
    commonly scoured by the K9B Reef but where the former is present a high gold tenor is associated with a small
    pebble conglomerate. Encouraging K8 intersections were reported and this orebody is therefore considered to
    represent a future upside potential in the Kimberley East Project area.
    Definitive Feasibility Study
    Work on the independent DFS being carried out by mine engineering firm, Bara Consulting, on the Qala Shallows
    is progressing well. The production model was defined in April 2021 and has been updated post-period for the
    restated JORC resource on completion of the infill-drilling program. All engineering work proceeded
    concurrently with exploration work however delays at the lab have had caused a minor delay on timing of DFS
    reporting which is now scheduled for late August.
    All surface infrastructure design, geotechnical engineering, underground excavation and infrastructure,
    equipment requirements and bulk engineering supply were completed during the period. The updated resource
    model was provided at the end of the reporting period, requiring an update to the DFS mine design and
    scheduled to produce a production profile for the life of the Qala Shallows. The Company will also now look to
    finalise and release the overall mine production targets (i.e. incorporating all stages identified by the prior
    scoping study) based on the previous scoping level study and taking into account the recently upgraded resource
    categories for the early mining stage resulting from the infill drilling campaign.
    Quotes were received during the reporting period from transport, mining and civil engineering contractors for
    cost inputs for the DFS and execution of the project. The DFS financial model is being updated with available
    inputs, all engineering disciplines are to be aligned with the final production inputs, with the final review and
    verifications to be completed. Engagement with proposed principal contractors is now accelerating, focussing
    on the early works and the DFS scope of work. Onsite meetings have been held to clarify the scope and the final
    terms for the early works.
    The DFS technical reports are due for completion late August.
    Mining Right Application
    South Africa’s Minister of Forestry, Fisheries and the Environment dismissed all three appeals lodged against the
    DMRE Environmental Authorisation approval at the end of March 20214
    . The Company’s team had already
    commenced re-engagement with the DMRE officers to expedite the grant of the mining right. The DMRE’s
    regional office was negatively impacted by a further wave of COVID-19 in Gauteng province which resulted in
    periodic office closures with lockdown measures increased.
    WWI worked closely with legal counsel and stakeholders to advance the MR application to the DMRE’s National
    Office in Pretoria during the reporting period. Subsequent to the reporting period, West Wits received formal
    ASX Announcement and Media Release
    29 July 2021
    communication from South Africa’s Director General of DMRE that the Company’s mining right application has
    been granted in terms of section 23(1) of the Mineral and Petroleum Resources Development Act, 2002 (Act 28
    of 2002)1
    . This milestone clears the path for proceeding with finalisation and execution of the mine plan. Most
    importantly the MR secures tenure over the tenement going forward for over 20 years with West Wits publicly
    approved by the Government as the approved operator. This security of tenure also provides the Company with
    the necessary platform and credentials to seriously negotiate and finalise arrangements with key third parties
    including mining and transport contractors, treatment plants and potential debt financiers. Now that the mining
    right has been granted these discussions are progressing quickly with a range of parties.
    AUSTRALIA
    Mt Cecelia, Paterson Province (100%)
    Ground geophysical surveys at Mt Cecelia were delayed from initial Jun-20 timing to early August due to
    availability of exploration crews in Western Australia resulting from COVID-19 border closures. WWI has
    engaged local specialist team Wireline Services Group (“WSG”) to perform a MLTEM survey consisting of 16
    Lines totalling 14.2km across the 4 priority targets identified in Southern Geosciences Consultants (“SGC”) HEM
    Survey Report5
    . SGC will perform analysis and reporting of WSG’s MLTEM survey data with survey results
    expected near the end of the September 2021.
    CORPORATE
    Cash & Financing
    West Wits maintains a cash position with $980k cash in hand as at 30 June 2021.
    The Company has commenced discussions with debt funders and investors. The recent granting of the mining
    right at the WBP, combined with the Definitive Feasibility Study on the Qala Shallows nearing completion, has
    resulted in significant interest in WWI from a broad range of financiers in South Africa, Australia and other
    countries, which gives the Company a high level of confidence it is now well placed to secure its funding
    requirements in the short term.
    COVID-19 Impact
    The impact of the COVID-19 pandemic has largely been confined to delays in the mining right application
    approval process and mobilisation of the exploration field team to Mt Cecelia as detailed earlier in the activities
    report. The Company does not expect the pandemic to negatively impact its ability to access financing. It is
    important to note that the mining industry in South Africa is fully functional, following strict protocols.
    A second phase of exploration to perform geological
    mapping and sampling at each target area is currently
    scheduled for early September.
    The 2021 field program is expected to define drill
    targets for the 2022 field season at the highly
    prospective Mt Cecelia Project in the East Pilbara.
    Figure 3: Eight SGC target zones (magenta)
    recommended for follow-up. Conductor axes
    marked by lines (bright red, yellow and blue)
    together with magnetic lineaments (brown)
    on SKYTEM CH15Z component image.
    ASX Announcement and Media Release
    29 July 2021
    The Company continues to monitor the ongoing COVID pandemic to identify and mitigate any associated risks
    to operational and corporate activities in achieving the business objectives.

 
watchlist Created with Sketch. Add WWI (ASX) to my watchlist
(20min delay)
Last
1.7¢
Change
0.002(13.3%)
Mkt cap ! $43.20M
Open High Low Value Volume
1.5¢ 1.7¢ 1.5¢ $45.00K 2.823M

Buyers (Bids)

No. Vol. Price($)
1 250000 1.6¢
 

Sellers (Offers)

Price($) Vol. No.
1.7¢ 1561158 9
View Market Depth
Last trade - 16.10pm 12/07/2024 (20 minute delay) ?
WWI (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.