    In the best case scenario that these wells are all that are required they need to:

    1. Run the 5 wells for 6 months
    2. Develop a full field model from the pilot data and get 2P reserves
    3. Field development plan and take FID
    4. Plan a major drilling campaign and execute it
    5. Build whatever gas infrastructure they need to prcoess and get it to market

    Realistically 2024 is pushing it now. I did previously say 2025 at the earliest. Even then it's going to take at least 12 months to ramp up to 30TJ/d. Senex were able to get first gas from Atlas in 2 years but only barely and they didn't need to pilot it first.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
5.8¢
Change
0.002(3.57%)
Mkt cap ! $43.22M
Open High Low Value Volume
5.7¢ 5.8¢ 5.7¢ $10.39K 181.5K

Buyers (Bids)

No. Vol. Price($)
2 572377 5.7¢
 

Sellers (Offers)

Price($) Vol. No.
5.9¢ 185000 2
View Market Depth
Last trade - 15.55pm 19/06/2025 (20 minute delay) ?
CTP (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.