I calculate 17 days at 35 metres a day from start on 26 sept to...

  1. 2,776 Posts.
    lightbulb Created with Sketch. 141
    I calculate 17 days at 35 metres a day from start on 26 sept to 13 oct for approx 600metres depth.
    So next results at 2200 metres is in 2200-600= 1600metres /35 a dy = 46 days.

    Next target is 3500 metres at 35metres a day is 3500-2200=1300/35= 37 days.
    Total time calculated at 35metres a day is 83 days.

    However this must be wrong as the response says no change to schedule .
    "As announced on 26 September 2022, Mukuyu-1 is expected to take 50 – 60 days to
    complete and there is no update to the guidance at this point."

 
watchlist Created with Sketch. Add IVZ (ASX) to my watchlist
(20min delay)
Last
6.3¢
Change
0.000(0.00%)
Mkt cap ! $89.32M
Open High Low Value Volume
6.3¢ 6.3¢ 6.1¢ $45.57K 732.6K

Buyers (Bids)

No. Vol. Price($)
2 115000 6.2¢
 

Sellers (Offers)

Price($) Vol. No.
6.3¢ 132559 5
View Market Depth
Last trade - 15.36pm 01/07/2024 (20 minute delay) ?
IVZ (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.