Oh no.. The management have just announced up to a 18 month delay on key milestones!!!
In May's presentation
Management announced to have finance completed Q3 2021 - now its 2H 2022 (a delay of anywhere between 12 and 18 months)
They announced that they would be construction ready Q3 2021 - now its 1H 2022 (a delay potentially of up to a year)
They announced that completion of financing was due Q3 2021 - now its 2H 2022 (a delay of anywhere between 12 and 18 months)
They announced to have first production Q4 2023 - now its 2H 2024 (a delay of anywhere between 12 and 15 months)
WITH NO EXPLANATION!!!
I have raised my concerns before on delays being added but this is a major CF and leads me to believe there are some major problems that we don't know about and they have put this out under a "rosy project update" on nothing more than recent news that has just been out.
- Forums
- ASX - By Stock
- Ann: Rhyolite Ridge Project Update
Oh no.. The management have just announced up to a 18 month...
Featured News
Add INR (ASX) to my watchlist
(20min delay)
|
|||||
Last
28.3¢ |
Change
-0.008(2.59%) |
Mkt cap ! $666.3M |
Open | High | Low | Value | Volume |
29.0¢ | 29.0¢ | 27.5¢ | $767.7K | 2.694M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
12 | 541860 | 28.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
28.5¢ | 105676 | 15 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
12 | 646064 | 0.280 |
11 | 550326 | 0.275 |
12 | 569727 | 0.270 |
8 | 319333 | 0.265 |
9 | 252147 | 0.260 |
Price($) | Vol. | No. |
---|---|---|
0.285 | 33642 | 9 |
0.290 | 394184 | 11 |
0.295 | 103509 | 4 |
0.300 | 192967 | 8 |
0.305 | 319408 | 7 |
Last trade - 11.37am 01/11/2024 (20 minute delay) ? |
Featured News
INR (ASX) Chart |