@Captain Kiethy
As you've pointed out, commissioning was meant to take four months. As at 03 Jan 23, construction was 98% complete and commissioning was 90% complete. Almost a year on, and it's still not sorted.
Construction and commissioning of other lithium production operations in Salta Province are on schedule (Eramine at Centenario Ratones and POSCO at Sal De Oro). They've shown that construction in the same remote area can be achieved on time and according to plan, provided proper planning was conducted.
Construction of AGY's 2 ktpa plant took twice as long as planned (almost two years), but setting that aside, commissioning is still well and truly delayed. I think we're past the point of blaming COVID and supply chain delays, as other companies in the same area seem to manage these challenges just fine.
- Forums
- ASX - By Stock
- AGY
- Ann: Rincon Lithium Project - Progress Update
Ann: Rincon Lithium Project - Progress Update, page-114
-
- There are more pages in this discussion • 83 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add AGY (ASX) to my watchlist
|
|||||
Last
8.5¢ |
Change
-0.008(8.60%) |
Mkt cap ! $123.7M |
Open | High | Low | Value | Volume |
9.0¢ | 9.3¢ | 8.5¢ | $362.9K | 4.093M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
9 | 459867 | 8.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
8.7¢ | 93664 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
9 | 459867 | 0.085 |
3 | 99873 | 0.084 |
4 | 169062 | 0.083 |
3 | 336585 | 0.082 |
2 | 114691 | 0.081 |
Price($) | Vol. | No. |
---|---|---|
0.087 | 93664 | 1 |
0.088 | 232558 | 1 |
0.089 | 69615 | 2 |
0.090 | 91167 | 2 |
0.091 | 52101 | 2 |
Last trade - 16.10pm 15/07/2024 (20 minute delay) ? |
Featured News
AGY (ASX) Chart |
The Watchlist
RCE
RECCE PHARMACEUTICALS LTD
James Graham / Dr Alan Dunton, MD & CEO / Non-Executive Director
James Graham / Dr Alan Dunton
MD & CEO / Non-Executive Director
SPONSORED BY The Market Online