FAR 3.09% 47.0¢ far limited

Senegal resources update • Independent Resources Report...

  1. 130 Posts.
    lightbulb Created with Sketch. 56
    Senegal resources update
    Independent Resources Report completed by RISC for FAR’s FAN oil discovery and undrilled
    exploration prospects, offshore Senegal

    2C Contingent recoverable oil resource of 198mmbbls* in the FAN discovery
    Undrilled prospects in total have prospective resources of 673mmbbls oil (best estimate)*
    Joint venture intends to progress appraisal plans for the FAN South and SNE north oil
    discoveries

    A review of the SNE oil field is expected mid-year
    FAR (ASX:FAR) has completed detailed geotechnical studies and reviewed the contingent resources
    attributed to the FAN discovery and prospective hydrocarbon resource potential in its Rufisque,
    Sangomar and Sangomar Deep (RSSD) Permits, offshore Senegal.
    The RSSD blocks cover an area of approximately 7,500kms2 and are home to the giant SNE oil field,
    discovered in 2014 by FAR and its partners in a two-well exploration drilling campaign offshore
    Senegal. The discovery of the SNE oil field and oil in the FAN-1 well (that was drilled into the deepwater
    FAN prospect) were the first wells to be drilled in the deepwater offshore Senegal and opened up what
    is now a global hotspot for oil and gas exploration.
    FAR and its joint venture partners have
    completed the appraisal drilling over
    the SNE oil field in the 2016 and 2017
    drilling campaigns and the field is
    currently progressing towards Final
    Investment Decision (“FID”) in 2019
    following the approval of the
    exploitation plan by the Government of
    Senegal which is expected by the end of
    2018.
    The SNE field development will be
    phased and it is anticipated that nearby
    discoveries that are within tie-back
    distance of the SNE field, will be
    developed in later phases. The focus of
    the joint venture has to date been to
    mature a commercial development of
    the SNE field before finalising
    assessment of these tie back
    opportunities.

    Figure 1: Location of all wells drilled to date in FAR’s Senegal permits
    * Refer to Cautionary Statement in this report (page 4) relating to estimates of prospective resources Page 2
    The FAN discovery well results (refer to ASX announcement dated 7 October 2014) has been evaluated
    by FAR and an Independent Resources Report for discovery has been completed by RISC Operations
    Pty Ltd (“RISC”).
    The FAN discovery contingent resource estimate detailed in Table 1 below have been calculated based
    on FAN-1 well log interpretation and mapping using the 3D seismic and bare set out in RISC’s report
    and assessment of the probabilistic resource evaluation carried out by FAR in accordance with industry
    standard SPE-PRMS definitions. A development project is contingent on further appraisal, formulation
    and approval of a field development plan and financing.

    Table 1. Summary of oil contingent resources (MMstb) included in RISC’s March 2018 report
    Column 1 Column 2 Column 3 Column 4 Column 5 Column 6 Column 7
    0 Gross Net Attributable
    1 1C [/COLOR] 2C 3C 1C 2C 3C
    2 FAN Discovery (MMstb) 30 198 637 4 27 87

    1. Gross are 100% of the resources attributable to the licence.
    2. Net attributable are reported on the basis of FAR’s current working interest share of 15%. Petrosen has an option to increase its working
    interest through the exploitation phase which would reduce FAR’s working interest to 13.7%.

    3. The contingent estimates are not adjusted to reflect the Production Sharing Contract entitlement on net economic interest basis.
    The FAN discovery is approximately 20kms from a development hub planned at the SNE field and hence
    is well within tie back distance estimated to be approximately 30kms. FAR has assessed the SNE field
    to contain 641mmbbls oil* (96mmbbls net to FAR, see ASX anouncement dated 23 August 2016).
    In the 2017 drilling campaign, FAR also drilled two new discoveries, FAN South and SNE North (as seen
    in Figure 1 alongside the location of the SNE Field and FAN discovery). Submissions have been made
    to the Government of Senegal seeking approval to undertake appraisal work programs to understand
    the potential commerciality of FAN South and SNE North as tie backs to the SNE Field development.
    FAR has further reviewed the undrilled prospects, integrating data from the 3D seismic survey acquired
    in 2015, reprocessed data from the existing 3D survey and data from the 11 successful oil wells now
    drilled in the RSSD acreage. These prospects have been reviewed by RISC and an Independent
    Resources Report for these prospective resources has been provided to FAR. Table 2 below details the
    prospective resource inventory in the RSSD acreage as reviewed by RISC.
    Table 2:
    Summary of RSSD Prospective Resources
    * Refer to Cautionary Statement in this report (page 4) relating to estimates of prospective resources Page 3
    FAR Managing Director Cath Norman said,
    “The eleven successful oil wells drilled to date in our
    acreage offshore Senegal are testimony to the fantastic opportunity FAR has captured and continues
    to mature for our shareholders. Alongside the giant SNE field, the FAN, FAN South and SNE discoveries
    are all within tie-back range of the planned hub development over SNE. The addition of more oil to the
    future phases of the development not only extends the life of the field but improves the longer-term
    economics of the development and revenues for the people of Senegal.
    This province, and in particular our RSSD acreage, has had so few wells drilled, has rich source rocks
    and excellent reservoirs - so has good potential to unlock more oil when these undrilled prospects are
    tested in the future. Adding 198mmbbls of 2C oil resource in the FAN discovery to the 641mmbbls FAR
    has assessed for the SNE discovery totals an enviable 123mmbbls of 2C resources net to FAR and
    development of these barrels will be underpinned by FID planned in 2019”.
 
watchlist Created with Sketch. Add FAR (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.