    we sort of knew that

    Public record pursuant to s. 39 of the Environmental Protection Act 1986
    Proposal title: HyEnergy Green Hydrogen and Ammonia Project
    Proposal location: Shire of Carnarvon, Gascoyne Region, Western Australia
    EO number: APP-0025048
    Date referral received: 14-12-2023 Date more information received: N/A
    Referrer: Proponent Proponent: Province Resources Limited
    Potential significant effects:
    There are potential impacts on: benthic communities and habitats, coastal processes, marine
    environmental quality, and marine fauna from the construction and operation of the port,
    desalination plant and associated marine elements of the proposal; flora and vegetation from
    clearing and disturbance, introduction of weeds, disease and pests, and ongoing operation;
    terrestrial fauna from the clearing or modification of habitat, collision with infrastructure, and
    ongoing operation; subterranean fauna from groundwater drawdown and construction
    related impacts; inland waters from changes to hydrological processes; air quality from
    emissions of nitrous oxides and carbon monoxide; greenhouse gas emissions from
    construction related emissions, and social surroundings from disturbance of Aboriginal and
    European Heritage sites, and impacts to visual amenity and recreational use.
    Preliminary key environmental factors: benthic communities and habitat, coastal
    processes, marine environmental quality, marine fauna, flora and vegetation, subterranean
    fauna, terrestrial fauna, inland waters, air quality, greenhouse gas emissions, social
    surroundings
    Public comment on referral information:
    Do not assess: 0
    Assess: a) Referral information 0
    b) Environmental review - no public review 0
    c) Public environmental review 6
    Total submissions: 6
    Decision: s. 38G(1) – Assess
    Level of assessment:
    Public Environmental Review, as required under s.40(2)(b) of the Environmental Protection
    Act 1986
    Other details
    EPA-prepared Environmental Scoping Document
    Public review period for Environmental Review Document (4 weeks)
    2
    OFFICIAL
    Explanation of decision:
    Several preliminary key environmental factors are complex. Detailed assessment is required
    to determine the extent of the proposal's direct and indirect impacts, and whether the EPA
    environmental factor objectives can be met.
    Appeals: Decision is not appealable.
    Prof. Matthew Tonts
    CHAIR
    Delegate of the Environmental Protection Authority Date: 31 January 2024
 