tt2000, you were on the money
"expected to take approximately 10 weeks for this body of work to be completed prior to
commissioning"
We know GMC never make any deadlines.
So it is highly likely that smelters will arrive on site in 2 weeks, and take 20 weeks from then to commissioning - making it early next year at best..."
Its already dragged out another 10 weeks since the previous announcement a couple of days ago.
Therefore mid 2019 is closer to the truth. When I suggested late 2018 some months ago all the GMC cheer squad said no way it will be up and running soon.
What a joke.
- Forums
- ASX - By Stock
- GMC
- Ann: Smelter Arrival Update
Ann: Smelter Arrival Update, page-3
-
- There are more pages in this discussion • 60 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add GMC (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
CCO
THE CALMER CO INTERNATIONAL LIMITED
Anthony Noble, MD & CEO
Anthony Noble
MD & CEO
Previous Video
Next Video
SPONSORED BY The Market Online