Looks like four more weeks for the flow rates
'The Easternwell 106 will demobilise from the West Erregulla 2 site over the next two weeks before the production flow testing package is called out to site. The flow test is expected to commence in early October and activities will take approximately two weeks to gather flow and pressure data from the reservoir'.