Sure. Beyond the technical problems, and failure to deliver agreed infrastructure on time, we have constant communications failures (perhaps simply lies).
Every official announcement covering Walyering construction has been at best a failure, at worst intentional deception.
STX estimates of Walyering completion, and/or first gas sales, are listed chronologically below.
15th August 2022 - Q1 2023
19th October 2022 - Q1 2023
14th December 2022 - Q1 2023
12th January 2023 - Q1 2023
2nd March 2023 - "early this year" 2023
14th March 2023 - "Construction and commissioning estimated to take approximately 6 weeks"
- "Commencement of production and gas sales is expected to occur in the month of April"
17th May 2023 - "Construction ongoing with start-up still on track for 1H/23"
19th June 2023 - "Construction well progressed, mechanical completion targeted within the next two weeks"
3rd July 2023 - "commissioning of the field will be delayed into Q3/23"
- Forums
- ASX - By Stock
- STX
- Ann: Talon Transaction
Ann: Talon Transaction, page-19
Featured News
Add STX (ASX) to my watchlist
(20min delay)
|
|||||
Last
22.5¢ |
Change
0.010(4.65%) |
Mkt cap ! $644.7M |
Open | High | Low | Value | Volume |
22.0¢ | 23.0¢ | 22.0¢ | $1.056M | 4.706M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
5 | 262128 | 22.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
23.0¢ | 3834531 | 37 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
3 | 233652 | 0.225 |
9 | 1743287 | 0.220 |
19 | 1564612 | 0.215 |
30 | 1432635 | 0.210 |
13 | 804634 | 0.205 |
Price($) | Vol. | No. |
---|---|---|
0.230 | 2686449 | 24 |
0.235 | 2870266 | 22 |
0.240 | 3211588 | 17 |
0.245 | 1422159 | 21 |
0.250 | 3405130 | 29 |
Last trade - 16.10pm 08/11/2024 (20 minute delay) ? |
Featured News
STX (ASX) Chart |
The Watchlist
EQN
EQUINOX RESOURCES LIMITED.
Zac Komur, MD & CEO
Zac Komur
MD & CEO
SPONSORED BY The Market Online