Hi @2ic,
Based on the presentation slide you have provided, the pre-production buffer nominally sits within the $20.4m listed as Working Capital - Indicative provision during start-up & commissioning.
This $20.4m is a buffer (contingency if you like but poorly described on the presentation slide) and in addition to the pre-prod costs represented in the Stage 1 Upfront Capex (of $361m) in the lines labeled EPCM, Commissioning & Indirects of $49.9m and some of the items contained above Owners Costs (Ops Readiness, G&A and first fills. Site Prep, Mining Services Mobillisation) totalling $106.8m
As @AX-E stated in post above, to try reconcile to the dollar the latest ASX release to these original presentation slides will prove difficult.
- Forums
- ASX - By Stock
- Ann: Thunderbird Construction Over 75% Complete
Hi @2ic, Based on the presentation slide you have provided, the...
-
- There are more pages in this discussion • 5 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add SFX (ASX) to my watchlist
(20min delay)
|
|||||
Last
29.5¢ |
Change
0.003(0.85%) |
Mkt cap ! $116.4M |
Open | High | Low | Value | Volume |
29.5¢ | 30.0¢ | 29.5¢ | $18.61K | 62.83K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 8858 | 29.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
30.5¢ | 2068 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 8858 | 0.290 |
3 | 44491 | 0.285 |
6 | 12830 | 0.280 |
1 | 50000 | 0.275 |
1 | 19000 | 0.270 |
Price($) | Vol. | No. |
---|---|---|
0.305 | 2068 | 1 |
0.310 | 975596 | 3 |
0.320 | 97149 | 3 |
0.330 | 51540 | 1 |
0.335 | 40000 | 1 |
Last trade - 15.37pm 17/10/2024 (20 minute delay) ? |
Featured News
SFX (ASX) Chart |
The Watchlist
LPM
LITHIUM PLUS MINERALS LTD.
Simon Kidston, Non Executive Director
Simon Kidston
Non Executive Director
SPONSORED BY The Market Online