I'd be happy they finish the FEED first Monday was 2 years from...

  1. 902 Posts.
    lightbulb Created with Sketch. 241
    I'd be happy they finish the FEED first frown.png
    Monday was 2 years from the first FEED announcement and we still don't know when that will be completed. Should have been mid-2020 but as usual PB's timelines and estimates mean nothing

    2 November 2018

    TNG APPOINTS SMS GROUP TO COMMENCE FRONT-END ENGINEERING AND DESIGN (FEED) FOR ENTIRE MOUNT PEAKE PROJECT AND PROVIDE FIXED-PRICE EPC PROPOSAL

    SMS group to commence comprehensive FEED (Front-End Engineering and Design) for TNG’s Mount Peake Vanadium-Titanium-Iron Project in the NT.



    February 2019

    Company Update Presentation

    ► Extensive development studies completed; feed (front-end engineering & design) underway



    March 2019

    Company Presentation, 121 Conference Hong Kong

    ► Extensive development studies completed; feed (front-end engineering & design) underway



    May 2019

    Corporate Presentation

    ► Extensive development studies completed; FEED (front-end engineering & design) underway



    19 August 2019

    UPDATE ON FRONT-END ENGINEERING AND DESIGN FOR THE MOUNT PEAKE PROJECT



    17 December 2019

    TNG SHAREHOLDER NEWSLETTER

    The final debt requirement will be determined upon completion of the FEED study, which is expected to be finalised in mid-2020, subject to factors outside of the Company’s control.



    4 February 2020

    MOUNT PEAKE PROJECT DEVELOPMENT UPDATE

    TNG’s strategic engineering and development partner, the German-based metallurgical engineering firm SMS group (“SMS”), has been advancing the comprehensive FEED study for the Project.


    We are very pleased with the progress made by our project development and implementation team so far, and particularly the progress made by SMS on the FEED study as its advances towards the delivery of an EPC Proposal.



    31 March 2020

    MOUNT PEAKE PROJECT & COVID-19 UPDATE

    the Company confirms that key work streams of the FEED study are continuing with SMS, however the timing of the FEED study completion is likely to be impacted; the Company is not expecting any major delay but this is subject to further developments of the rapidly changing COVID-19 global situation



    19 May 2020

    MOUNT PEAKE VANADIUM-TITANIUM-IRON PROJECT DEVELOPMENT UPDATE

    TNG and its strategic engineering and development partner, the German-based metallurgical engineering firm SMS group (“SMS”), have continued to advance the key work streams within the comprehensive FEED study for the Mount Peake processing plants related to design and engineering



    10 August 2020

    MOUNT PEAKE VANADIUM-TITANIUM-IRON PROJECT DEVELOPMENT UPDATE

    TNG and its strategic engineering and development partner, the German-based metallurgical engineering firm SMS group (“SMS”), have continued to advance completion of the key work streams within the comprehensive FEED study for the Mount Peake processing plants related to design and engineering.



    September 23 2020

    Annual Report 2020

    Despite the challenges associated with COVID-19, our team and partners were able to progress an extensive body of work during the year.

    Fortunately, we have been able to continue advancing pre-development activities for the world-class Mount Peake Vanadium-Titanium-Iron Project in the Northern Territory with limited disruptions, with the Front-End Engineering and Design (“FEED”) Study, permitting and approvals being our main focus.

    During the year, our strategic development partner, SMS group, made great inroads into the detailed FEED Study with the completion of the first two phases, FEL - 0 and FEL - 1, and of the majority of works related to FEL - 2.



    26 October 2020

    September 2020 Quarterly Activities Report

    Key work streams within the comprehensive Front-End Engineering and Design (“FEED”) study for the Mount Peake Project continued to be advanced during the quarter.




    TBC...
 
watchlist Created with Sketch. Add TVN (ASX) to my watchlist
(20min delay)
Last
5.0¢
Change
0.001(2.04%)
Mkt cap ! $86.37M
Open High Low Value Volume
4.9¢ 5.1¢ 4.9¢ $119.9K 2.412M

Buyers (Bids)

No. Vol. Price($)
2 86483 5.0¢
 

Sellers (Offers)

Price($) Vol. No.
5.1¢ 75153 1
View Market Depth
Last trade - 16.10pm 30/08/2024 (20 minute delay) ?
TVN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.