    That makes sense. The first well spudded sometime around 22nd Feb and completed late March (approx. 5 weeks). They then spent approx 2 weeks mobilising/preparing for the second well spud (taking us to mid-April).
    So, based on the second well spud date of mid-April, then we are already 3 weeks into the drilling, and hopefully only be approx. 2 weeks away from completion of this last government well (assuming the same 5 weeks drilling timeframe). Hopefully, anyway.
 
watchlist Created with Sketch. Add MAY (ASX) to my watchlist
(20min delay)
Last
2.3¢
Change
0.002(9.52%)
Mkt cap ! $77.51M
Open High Low Value Volume
2.2¢ 2.3¢ 2.2¢ $83.23K 3.644M

Buyers (Bids)

No. Vol. Price($)
5 310691 2.2¢
 

Sellers (Offers)

Price($) Vol. No.
2.4¢ 3542587 7
View Market Depth
Last trade - 16.10pm 16/08/2024 (20 minute delay) ?
MAY (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.