I think you are wrong about the factory being delayed.
The photo in the Q4/23 update shows the foundations complete so the first 2 instalments $1.4m and $2.1 m would have happened in 2023.
The Photo in the Q2/24 update shows the roof on but the commentary says the external finishes are still being designed so Its likely that the third instalment of $2.1m happened in Q1 /24 and the forth instalment of $2.1m happened in Q2/24
The final four $1.4m instalments will happen in H2/24 and then the last $700k in Q4 /26 it seems with thigs going pretty much to plan.
I have been told If sales don't pick up they will lease the building. let's hope that's not necessary.
- Forums
- ASX - By Stock
- VMT
- Ann: Vmoto's 2Q24 Market Update
Ann: Vmoto's 2Q24 Market Update, page-32
Featured News
Add VMT (ASX) to my watchlist
(20min delay)
|
|||||
Last
11.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $48.09M |
Open | High | Low | Value | Volume |
11.0¢ | 11.5¢ | 11.0¢ | $42.72K | 387.7K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 50000 | 11.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
12.0¢ | 170793 | 4 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 50000 | 0.110 |
4 | 102144 | 0.105 |
5 | 175000 | 0.100 |
1 | 30000 | 0.095 |
1 | 37500 | 0.080 |
Price($) | Vol. | No. |
---|---|---|
0.120 | 170793 | 4 |
0.125 | 278283 | 6 |
0.130 | 268255 | 5 |
0.135 | 82972 | 4 |
0.140 | 578739 | 2 |
Last trade - 14.52pm 15/11/2024 (20 minute delay) ? |
Featured News
VMT (ASX) Chart |
The Watchlist
ACW
ACTINOGEN MEDICAL LIMITED
Will Souter, CFO
Will Souter
CFO
Previous Video
Next Video
SPONSORED BY The Market Online