    Environmental Clean Technologies Limited (ASX: ECT) (ECT or Company) is pleased to provide the following update on its India project.

    The Company requests an extension to the current suspension of trading through to and inclusive of 31 May 2019.

    Recent visits by ECT personnel to India and further correspondence with project partners NLCIL and NMDC continue to show progress (Objective 2) and provide confidence in the expected outcome. Two critical objectives are yet to be fully confirmed, namely, Objective 6 and 7, as set out below.

    Background

    The Company requested a voluntary suspension in the trading of its securities from the ASX on 15 March 2019 until 1 April 2019 pending feedback from its India project partner, NMDC on the status of its process to consider and approve the signing of the Research Collaboration Agreement (RCA).

    On 29 March 2019, an extension to the voluntary suspension was granted until 22 April 2019 to address seven (7) key objectives in achieving certainty around the process and timeframes.

    An update on the progress of the outlined objectives was provided on 18 April and 6 May 2019, with a further extension granted by the ASX until 17 May 2019 to allow time to pursue confirmation of timing.

    Objectives

    Objective 1: NMDC’s request for extension of the MOU to allow for adequate time to complete their internal processes.

    Status: complete

    Objective 2: Agreement to, and signing of, a further MOU extension by NLC India Limited (NLCIL), NMDC and ECT.

    Status: complete, all parties have signed the MOU Extension letter, providing an extension to 31 May 2019 for completion of project approvals by NMDC.

    Objective 3: Confirmation from NLCIL that all pre-existing approvals remain on-foot subject to the granting of the extension of the MOU as per 1.

    Status: complete

    Following a series of meetings between ECT and NLCIL over the past several weeks both companies are pleased to confirm that all board approvals remain on foot.

    Objective 4: Confirmation that the upcoming Indian federal election does not place NMDC or NLCIL into “caretaker mode”.

    Status: complete

    NLCIL and NMDC have confirmed that there are no such ‘caretaker mode’ provisions which apply to Centralised Public Sector Entities during an election period. ECT notes that all regional polling events have now been completed, and election results are due for announcement on 23 May. There has been no impact on the Company’s dealings with NLCIL or NMDC.

    Objective 5: Distribution of the final Research Collaboration Agreement, schedules and signing protocol.

    Status: complete

    As previously stated, the final ‘frozen’ form of the RCA was distributed to all parties on 15 April 2019. Further, ECT has discussed the signing protocol requirements and is comfortable that these can be implemented promptly once the pending NMDC approval requirements are concluded. As outlined under objective 3 above, NLCIL remain ready, willing and able to countersign upon NMDC’s approval.

    Objective 6: Confirmation from NMDC that all internal processes have been completed (ahead of objective 7 below).

    Status: in progress

    NMDC continue to progress their internal review process and all parties remain respectful of the need for completion of necessary approvals and formalities and remain patient and supportive in this regard.

    As reported previously, there are no outstanding matters to be resolved, other than the final formal approval from NMDC, hence completion of this objective will only be ultimately confirmed upon completion of Objective 7 below.

    Objective 7: Confirmation from NMDC of a date for their next board meeting and their intention to take the project proposal forward for a decision.

    Status: in progress

    NMDC have announced their board meeting for 28 May 2019.

    On the basis that Objective 6 is met, ECT and NLCIL are awaiting NMDC’s confirmation that the project will be included on the agenda for consideration.

    ECT executives will be returning to India over the next few days to meet with and discuss these final arrangements with both NMDC and NLCIL and ensure all necessary support is provided towards a positive outcome for the project and partners.

    The Company has requested an extension to the current suspension of trading through to and inclusive of 31 May 2019 to provide the necessary timeframe for completion of the NMDC Board meeting, formalisation of meeting minutes and outcomes to be made available to ECT.

    For further information, contact:

    Glenn Fozard – Chairman [email protected]


    Tick Tock
 
watchlist Created with Sketch. Add ECT (ASX) to my watchlist
(20min delay)
Last
0.3¢
Change
-0.001(25.0%)
Mkt cap ! $9.515M
Open High Low Value Volume
0.4¢ 0.4¢ 0.3¢ $297 79.57K

Buyers (Bids)

No. Vol. Price($)
55 17643627 0.3¢
 

Sellers (Offers)

Price($) Vol. No.
0.4¢ 14484105 27
View Market Depth
Last trade - 15.59pm 19/07/2024 (20 minute delay) ?
ECT (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.