It's difficult to see isn't it.
I have been asking on the STX thread how realistic it is. It was suggested that 100m of pipeline per day is achievable on farmland. We have 2100m to lay. We also need to build the plant at the same time. Technically achievable in late June or perhaps early July if they work 7 days around the clock as advised by STX.
Problem is, I don't think they have actually started yet. We have seen pictures of W5 workover, the solar panels, and the APA Parmelia connection. No pictures of the plant or pipeline.
STX still have the application for construction and commissioning of the Walyering Plant application as "awaiting assessment" at DMIRS last status date 2nd May 2023. That looks like the roadblock. Perhaps those on here who have a line of communication to Colby and/or Stuart could speak to them and get some clarification.
https://ace.dmp.wa.gov.au/ACE/Public/PetroleumProposals
- Forums
- ASX - By Stock
- TPD
- Ann: Waylering Update
Ann: Waylering Update, page-90
-
-
- There are more pages in this discussion • 43 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)