    15th Feb - Strike will finish casing and cementing of the first intermediate hole section and will then commence drilling the 12-1/4” second intermediate hole section.

    That would likely have taken 3 days. Cement to dry then pressure test.

    Then drill string has to get back to 2600m which would take 1/2 - 3/4 of a day.
    assumption - no problems in doing the above.
    Drilling again mid-late 19th Feb at earliest.

    Rate of progress likely slower as you get to greater depths. 100m / day ?
    likely depth now 3000-3300m IMO
    (also a drill bit change may be needed as they drill into harder formations)

    2nd intermediate section TD likely around 4000m. That will require drill string out, case, cement, pressure test, 4-5 days.

    Then drill string in with LWD tool to pass through wagina and KHC.

    IMO
 
watchlist Created with Sketch. Add STX (ASX) to my watchlist
(20min delay)
Last
19.5¢
Change
0.000(0.00%)
Mkt cap ! $558.7M
Open High Low Value Volume
0.0¢ 0.0¢ 0.0¢ $0 0

Buyers (Bids)

No. Vol. Price($)
1 10000 28.0¢
 

Sellers (Offers)

Price($) Vol. No.
18.0¢ 452905 4
View Market Depth
Last trade - 16.20pm 02/09/2024 (20 minute delay) ?
STX (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.