    15th Feb - Strike will finish casing and cementing of the first intermediate hole section and will then commence drilling the 12-1/4” second intermediate hole section.

    That would likely have taken 3 days. Cement to dry then pressure test.

    Then drill string has to get back to 2600m which would take 1/2 - 3/4 of a day.
    assumption - no problems in doing the above.
    Drilling again mid-late 19th Feb at earliest.

    Rate of progress likely slower as you get to greater depths. 100m / day ?
    likely depth now 3000-3300m IMO
    (also a drill bit change may be needed as they drill into harder formations)

    2nd intermediate section TD likely around 4000m. That will require drill string out, case, cement, pressure test, 4-5 days.

    Then drill string in with LWD tool to pass through wagina and KHC.

    IMO
 
watchlist Created with Sketch. Add STX (ASX) to my watchlist
(20min delay)
Last
20.0¢
Change
0.005(2.56%)
Mkt cap ! $572.1M
Open High Low Value Volume
19.5¢ 20.0¢ 19.0¢ $1.339M 6.792M

Buyers (Bids)

No. Vol. Price($)
23 674181 19.5¢
 

Sellers (Offers)

Price($) Vol. No.
20.0¢ 741329 6
View Market Depth
Last trade - 16.10pm 26/07/2024 (20 minute delay) ?
STX (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.