ECURITIES EXCHANGE ANNOUNCEMENT & MEDIA RELEASE
1 August 2008
$141.8M RECEIVED FOR THIRD EQUITY INSTALMENT
FOR KARARA IRON ORE PROJECT DEVELOPMENT
INCLUDES FIRST EQUITY CONTRIBUTION OF A$18.38 MILLION BY GINDALBIE
Gindalbie Metals Limited (ASX: GBG – “Gindalbie”) is pleased to announce the completion of payments totaling
A$141.8 million under the previously announced equity funding arrangements for the A$1.8 billion Karara Iron Ore
Project in Western Australia. This comprises a A$123.38 million payment by Gindalbie’s joint venture partner, Anshan
Iron & Steel Group Corporation (“AnSteel”), and Gindalbie’s first equity contribution of A$18.38 million.
The third payment by AnSteel reinforces its commitment to the rapid funding of the project and takes the cash balance
of the joint venture company, Karara Mining Limited (KML), to more than A$200 million to be applied to the
development of the project.
“This is another important milestone which brings the total equity payments by AnSteel to date to approximately A$228
million,” said Gindalbie’s Managing Director, Mr Garret Dixon.
“KML currently has more than A$200 million in available cash reserves which will be utilized for the ongoing pre-
development activities at Karara, including final engineering and design work and long-lead equipment items such as
the recent orders totaling approximately $70 million for two high pressure grinding rolls and four large ball mills.”
Under the terms of the Karara Joint Venture Development Agreement AnSteel has one final payment of $143.68
million to make in October as part of the conditions to earn its 50% stake in the project.
Payment Date Ansteel (A$ m) Gindalbie (A$ m) Status
February 2008
April 2008
July 2008
October 2008
50.00
55.00
123.38
143.68
--
18.38
143.68
9
9
9
Total payments 372.06 162.06
Also as part of the joint venture agreement Gindalbie can elect to borrow the full amount ($162.06 million) of its share
of the equity contributions from AnSteel as debt. As previously foreshadowed Gindalbie has now exercised that right
and negotiations are well advanced with the terms of the equity finance expected to be finalised by the end of the
September Quarter.
2
“This application to AnSteel eliminates the need for Gindalbie to raise equity funding in the current difficult period for
financial markets,” Mr Dixon said. “We expect that this finance will be provided at competitive rates, reinforcing the
strength of the joint venture and the significant benefits of having a joint venture partner with the depth and financial
capacity of AnSteel.”
Securing and underwriting the project debt is also one of AnSteel’s buy-in conditions and advanced discussions are
continuing with China Development Bank (CDB) to provide the senior debt finance of $1.4 billion for the Karara Project.
AnSteel has a good relationship with CDB and the Joint Venture expects to have the terms and conditions of the
finance in place by later this year.
- ENDS
Released by: On behalf of:
Nicholas Read Mr Garret Dixon/Mr Michael Weir
Read Corporate Managing Director/Investor Relations Manager
Telephone: (+61-8) 9388-1474 Telephone: (+61-8) 9480-8700
Mobile: (+61-8) 419 929 046 www.gindalbie.com.au
About Gindalbie Metals Ltd (ASX: GBG)
Gindalbie is well advanced towards achieving its vision of becoming a leading independent Australian iron ore company with
a diversified portfolio of magnetite and hematite production assets, located in the Mid West region of Western Australia.
The initial focus of Gindalbie’s growth strategy is the Karara Iron Ore Project, located 225km east of Geraldton, where it will
deliver initial production of Direct Shipping Ore (DSO) hematite in 2009 to be followed by production of high grade magnetite
concentrate and blast furnace quality pellets in 2010. Karara is being developed through a 50:50 Joint Venture with Ansteel,
one of China’s leading steel and iron ore producers.
Gindalbie’s longer term growth will be propelled by the exploration and development of its extensive 1,900 sq km tenement
portfolio, which includes numerous prospective magnetite and hematite exploration targets expected to deliver a long-term
pipeline of growth opportunities.
For further information, visit www.gindalbie.com.au
About Ansteel
Ansteel is currently one of China’s largest steel producers and is the major producer in the north-east region of China, with
crude steel production of 22 million tonnes, annual sales revenues in excess of US$11 billion and a profit of approximately
US$1.5 billion in 2006. Ansteel is considered to be one of the country’s key growth companies and has strong government
support in securing new sources of long-term iron ore supply through international investment.
Ansteel is developing a new integrated iron and steel making facility at Bayuquan, adjacent to the Port of Yingkou,
approximately 100km south-west of its current steel making facility in the city of Anshan. The new facility will have the
capacity of 6.5Mtpa of finished steel products and is the facility that the Karara products will feed upon commencement of
production.
For further information, visit www.ansteelgroup.com
- Forums
- ASX - By Stock
- ansteel stiil showing the cash
ECURITIES EXCHANGE ANNOUNCEMENT & MEDIA RELEASE 1 August 2008...
Featured News
Add GBG (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
CCO
THE CALMER CO INTERNATIONAL LIMITED
Anthony Noble, MD & CEO
Anthony Noble
MD & CEO
Previous Video
Next Video
SPONSORED BY The Market Online