Hi Bizzo
IMO after reading various company infO
it seems DARGUES first production will
commence during the first quarter of 2014 ???
FROM UML RELEASE 17 April 2013
Preliminary earthworks commenced at Dargues
Gold Mine on 11 February 2013 which will include
construction of site access roads, ROM pad and mine
box cut. As at 31 March 2013, 88,000 cubic metres
had been moved, representing approximately 50% of
the earthmoving task.
Recruitment of senior site personnel is progressing
well with the appointments of the General Manager,
Senior Mining Engineer, Safety Manger and
Environment & Community Manager.
Preparations for the mobilisation of plant and
underground development teams are similarly well
advanced.
Studies are also continuing to explore the economics
of processing of the Dargues gold concentrate at the
Kangaroo Flat CIL plant