I was just looking around and found an older slide regarding T3 in Botswana on the company website
http://www.modresources.com.au/#!MOD0040A(ASXAnn14April16)/zoom/c1mqa/dataItem-imzonjel
It was very interesting to see in this slide (& not in the latest presentation version of it) it listing the "Estimated true width of the Mineralised Sequence"
RC 11R = 70M
RC 12R = 40M
RC 13R = 45M
RC 14R = 80M (This is a 100M step-out to the West)
RC 15R = 79M (This is a 100M step-out to the East)
RC 16R = 74M (This is an additional 100M step-out to the East)
All the other holes were still only being planned/drilled at that point.
I'm sure you're drawn just like me to the fact the step out holes drilled towards the South have much thicker Mineralised Sequence's than the 3 holes we already have assay results for.
So we should be getting a higher number of Meter's with readings in these next set of assay results for each of those 3 holes that's for sure.
DDH01 should hopefully confirm & possibly enhance the 52M @ 2% CU recorded as its very close to the RC12 location.
DDH02 should hopefully confirm the RC11 location readings, encounter the expected geological fault & what lies beyond it.
Everything else after that is really new territory.
Exciting times
LOTM