RVR has been ramped up early. Thalanga Mine processing plant...

  1. 2,415 Posts.
    lightbulb Created with Sketch. 17
    RVR has been ramped up early.

    Thalanga Mine processing plant throughput has ramped up to annualised rate of 325ktpa

    • Mining and processing rates now exceed the design rate forecast in the Thalanga Restart Study (2015)

    • Ramp up completed ahead of schedule and approximately $1m under budget

    • Metallurgical recoveries and concentrate grades approaching Restart Study design parameters

    • 13,500 tonnes of low to medium-grade ore processed since production commenced with high grade ore now being blended into the mill feed as required

    • First concentrate deliveries will commence in the coming weeks and first cash flow is imminent thereafter.
 