• The main long-lead item, the primary ball mill has been fabricated by Outokumpu Technology
Australia and the largest mill component, the shell barrel, was delivered to Avebury site on 20 April
2007 - 17 days ahead of schedule.
• Engineering firm, Metplant of Perth relocated its construction team to the Avebury process plant
site in January-February and site construction offices are fully equipped and staffed.
• The project will mill 900,000 tonnes of ore producing 8,500 tonnes of nickel (“Ni”) in concentrates
pa. The revised business plan currently extends to June 2016 - to extend as resources expand.
• The main long-lead item, the primary ball mill has been...