On another site 4th July there was this
"I rang the company this morning to ask where the weekly update was [due yesterday] and see that the ann came about 5 minutes after i spoke with Laurence Roe. Apparently they thought it had been lodged.
The short version of our conversation was that drilling at Bandito would probably not be completed for another 10-14 days."
Given that they were 546 metres from td according to the update July 3 that puts news between 14th and 17th July.