So, when are the approximate production dates for our current development sites?
Production appears to begin in 2022,(Below) this may also in include Sal De Vida. I have not seen any production dates in relation to James Bay.
So, I would anticipate some more investment money rolling in prior to these sites starting up under the banner that the 2022 production figures may be seen as enhancing the share-price
ORE: Has –
OLAROZ STAGE TWO
Construction underway to expand Olaroz to produce an additional 25ktpa of lithium carbonate
Expected completion in H1 2022 and production to commence in H2
Production of primary grade lithium carbonate will ramp up over 2 years to full capacity
At the end of June, most infrastructure is complete, many ponds have been built and soda ash and carbonation plants are 10% and 14% complete respectively.
Additional accommodation facilities were completed in the quarter with over 65 0personnel on site
Lime plant #1 (services Stage 1) is fully operational and Lime plant #2 was commissioned in February providing additional capacity. Lime plant #3 will more than double the combined capacity of Plants 1 and 2 and will be completed in H2 2021
Construction of the carbonation plant and soda ash plant are 10% and 14% complete respectively. The soda ash plant is expected to be complete during 2021 and will service both Stages 1 and 2 providing additional efficiencies.