BTV batavia mining limited

BATAVIA TO ACCELERATE DEFLECTOR FEASIBILITYFOLLOWING POSITIVE...

  1. 2,257 Posts.
    BATAVIA TO ACCELERATE DEFLECTOR FEASIBILITY
    FOLLOWING POSITIVE SCOPING STUDY
    Highlights
    Batavia’s Managing Director, Mr Greg Durack, said that following completion of
    the Scoping Study on schedule, the Company had set an aggressive target of
    completing the Bankable Feasibility Study by August 2006.
    “We have already commissioned preliminary work for the Bankable Feasibility
    Study and we will now fast-track the study with definitive metallurgical test work
    on Deflector ore already underway,” Mr Durack said. “In addition, we have
    recently commenced the resource in-fill and extension drilling program at
    Deflector, which is targeting a further significant increase in the Deflector
    resource inventory from 775,000 gold equivalent ounces to 1 million gold
    equivalent ounces.”
    “Our objective is to advance the project towards production as rapidly as
    possible, in order to take advantage of the current strong commodity price
    environment, in conjunction with ongoing exploration to further increase the
    resource base and enhance the overall project parameters.”
    The process and infrastructure component of the Deflector Scoping Study was
    completed by Metplant Engineering Pty Ltd, and the Mining Study was completed
    by Snowden Mining Industry Consultants.
    PROCESS AND INFRASTRUCTURE SCOPING STUDY
    Batavia engaged Metplant Engineering Services Pty Ltd (Metplant) to undertake a
    scoping study to review the establishment of a gold/copper processing facility at
    the Gullewa site. The scoping study has identified the operating costs and level of
    capital expenditure required to install a suitable flotation and ancillary circuit to
    the existing processing plant at Gullewa.
    Where practicable, the Scoping Study was based on utilization of existing
    equipment, in conjunction with a value-added engineering approach to ensure
    that the plant will be basic, yet robust and technically suited to the required
    purpose.
    The study also reviewed recent and previous metallurgical test work in order to
    develop a suitable treatment flow sheet. The proposed flow sheet will incorporate
    crushing, grinding, flotation, concentrate dewatering and the production of gold
    bullion. The proposed treatment plant is designed to treat either oxide,
    transitional or primary sulphide ore types – covering all three types of
    mineralisation within the Deflector deposit.
    Enquiries:
    Greg Durack
    Batavia Mining Ltd
    + 61 (0)8 9327 0980
    Damian Delaney
    Batavia Mining Ltd
    + 61 (0)8 9327 0980
    Jan Hope & Partners + 61 (0)8 9388 1474
    www.bataviamining.com.au
    The capital cost for the processing facility and associated infrastructure is
    estimated at A $13.8 M. This cost has been prepared to an accuracy of plus or
    minus thirty (30) percent. An overall ten percent (10%) contingency is included
    in this estimate.
    The estimated operating costs for the Gullewa concentrator, including
    administration, is A$48.81 per tonne of ore processed for oxide and transitional
    material and A$37.53 per tonne of ore for primary material. This is based on mill
    throughout of 250 000 tonnes per annum. The higher unit operating costs for the
    oxide and transitional material is due to the use of a new copper specific
    chelating agent in the flotation process.
    MINING STUDY
    Batavia engaged Snowden Mining Industry Consultants Pty Ltd (Snowden) to
    complete a scoping study for mining of the Deflector deposit, including :
    �� a review of previous mining studies
    �� an open pit optimization and designs using inputs supplied by Batavia and
    Snowden
    �� underground development and stope designs below the base of the open
    pit
    �� a mine schedule incorporating open pit and underground mining
    �� an estimate of open pit capital and operating costs, derived by Snowden
    from similar operations in Western Australia
    �� an estimate of underground capital and operating costs derived from the
    2004 feasibility study and escalated to reflect increases in mining costs
    and
    �� a basic cash flow model using revenues, recoveries and processing and
    TC/RC costs provided by Batavia
    The open pit design reflects the changes in the metallurgical methods with
    related changes in costs and recoveries (higher processing costs and lower
    recoveries especially copper for the oxide and transitional material), while the
    mining cost has also been increased by 20% to reflect the current high demand
    for mining equipment and services. In general, higher costs are effectively off set
    by higher metal prices.
    The staged open pit design completed in the study contains 337,000 t at 5.73 g/t
    Au and 2.10% Cu at an overall strip ratio of 24.6:1
    The open pit provides just over 12 to 18 months of ore supply to the processing
    plant. Approximately 3 months of pre-strip will be necessary to access a suitable
    ore flow. The secondary pit in the Central Lode is a convenient location for the
    underground portal that can be established early in the life of the project and
    provide a relatively secure position to commence underground development.
    While the reefs are relatively narrow, small scale equipment and 2m high
    benches will ensure optimum extraction with minimal dilution and ore loss. The
    mining methods assumed 20% dilution and 2.5% ore loss modifying factors.
    For underground mining, the 2004 BFS identified that the deeper portions of the
    Deflector ore body between 200 mRL and 110 mRL could be mined from
    underground using a mechanized uphole benching method, mining in a “topdown”
    direction. Small pillars would be left to maintain local and regional
    stability; no backfill would be used.
    The uphole benching stoping method proposed in the 2004 BFS featured a
    minimum mining width of 1.5m and identified a potential mining inventory of
    181,000 t at 4.92 g/t Au and 1.17% Cu.
    Significant drilling at depth has extended the resource model and mine plan
    200m deeper to -80 mRL. Snowden’s mine plan identified a potential mining
    inventory between the base of a crown pillar (nominally 220 mRL) and -80 mRL
    of 1.06 Mt at 6.5 g/t Au and 1.1% Cu.
    Below 140 mRL (which includes material at higher than average Au grades) the
    resource is classified as Inferred. As such, the mine plan prepared for this deeper
    region is regarded “high risk” in terms of mineable tonnes and grade.
    Snowden’s mine plan is similar to that proposed in the 2004 BFS with the major
    differences being the increased depth and a change in cross-cut position to
    access the centre of each lode, rather than the ends. Underground labour and
    consumables costs were escalated 15% from the 2004 BFS (estimated in late
    2004).
    The overall life of the mining operation is approximately 5 ½ years.
    The open pit mine will produce approximately 25,000 to 30,000 tonnes per
    month for 12 months, and then 15,000 to 20,000 tonnes per month for the final
    eight months, as the underground mine is commissioned and brought into
    production.
    The portal position is located in the northern end of the Central Lode and reached
    after six months of open pit mining. Due to the close proximity of the portal to
    the first stope blocks, underground production commences after 3 months and
    reaches full production of 20,000 to 25,000 tonnes per month after 12 months.
    There is a six month period with ore sourced from both the open pit and
    underground mines.
    The decline priority is to access the deeper, higher grade ore below 60 mRL,
    which will be reached after approximately 24 months. Over the life of the mine
    the open pit produces 15,000 tonnes of concentrate containing 48,200 ozs Au
    and 3,900 tonnes Cu. The underground mine produces 63,400 tonnes of
    concentrate containing 193,600 ozs Au and 10,200 tonnes Cu.
    RESOURCE INFILL AND EXTENSIONAL DRILLING
    The Company commenced a major new drilling program on the Deflector Gold-
    Copper Project in mid-March 2006 comprising both in-fill and resource
    extensional drilling.
    A significant part of the mineral resource is in the Inferred category, which was
    included in the current Mining Study. The objective of the new drilling is to in-fill
    upper portion of the Inferred section in the West lode to bring into the Indicated
    resource category to increase the level of confidence.
    In addition to the in-fill drilling, resource extensional drilling is currently in
    progress to test depth extensions on both West and Central lodes. The objective
    is to increase the Mineral Resource to 1,000,000 Au Eq ozs.
    Batavia is aiming to complete this drilling program by the end of May 2006, to be
    followed by resource modelling.
    BANKABLE FEASIBILITY STUDY
    Following the positive outcome of the Scoping Study, Batavia has now
    commissioned preliminary work for the Bankable Feasibility Study on the
    Deflector Deposit, which it intends to fast track.
    Definitive metallurgical test work has recently commenced at Independent
    Metallurgical Laboratories on all three Deflector ore types, comprising both
    variability and closed cycle tests in order to satisfy design requirements.
    Metplant Engineering Services has been commissioned to complete the Process
    and Infrastructure component, and is also involved in supervising the
    metallurgical test work program.
    Planning discussions have also commenced with Snowden in order to complete
    the resource modelling, once the current drilling program is finished, and then to
    complete the final Mining Study for the Bankable Feasibility Study.
    The Company has set an aggressive schedule, targeting completion of the
    Bankable Feasibility Study in August 2006. The Bankable Feasibility Study is
    being undertaken to complete further studies and drilling and do a sensitivity
    analysis to verify all the outcomes and assumptions identified during the Scoping
    Study. A development decision on the Deflector Gold-Copper Project will be
    made dependent upon the outcome of the Bankable Feasibility Study.
    Greg Durack
    Managing Director
    3 April 2006

    wrxsti
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.