Pivot PlantAfter reading all these Hoohaa !I decided to find out...

  1. 123 Posts.
    lightbulb Created with Sketch. 34
    Pivot Plant
    After reading all these Hoohaa !
    I decided to find out what's going on directly from the builder : JinPeng Mining Co.
    https://jinpengmining.com/
    I talked to the project manager, Eddie.
    The main storys are as follows:
    1. Contract was signed last year, and they started the design and the first draft was approved by BEZ.
    2. Couples of months later, BEZ informed them that another site for the plant was chosen and the design needed to change to suit the new site. That's why there is bit of delay and not their fault.
    3. The first section of the plant has already arrived in Kuching port awaiting custom clearance.
    4. The second section is almost finish and can send to Kuching by the end of April.
    5. However, they still need to visit the site when the plant has arrived at the site before they can finalize the design of the electrical controlling systems. If everything go smoothly, that can be done by end of may or June.
    6. I actually called the office first thing in the morning, he was not in then, But he called me back which very good.
    Now, let wait for news about US$9.8 M. and focus on more positive stuff.


 
watchlist Created with Sketch. Add BEZ (ASX) to my watchlist
(20min delay)
Last
9.4¢
Change
0.000(0.00%)
Mkt cap ! $39.30M
Open High Low Value Volume
9.4¢ 9.4¢ 9.2¢ $26.15K 281.3K

Buyers (Bids)

No. Vol. Price($)
1 50930 9.4¢
 

Sellers (Offers)

Price($) Vol. No.
9.6¢ 10400 1
View Market Depth
Last trade - 16.10pm 24/05/2024 (20 minute delay) ?
Last
9.4¢
  Change
0.000 ( 1.08 %)
Open High Low Volume
9.5¢ 9.5¢ 9.2¢ 223458
Last updated 15.44pm 24/05/2024 ?
BEZ (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.