The power stations to be built at Ipswich & Gladstone will be each 500MW expandable to 1500MW.
1MW=1MJ/sec
Therefore 500MW=15.8PJ/year (assuming 100% utilization)
At 50% thermal efficiency, each 500MW station will need approx 30PJ/year energy input.
At full stretch both power stations at 1500MW will need energy input of 180PJ per year.
SXY has 79PJ in CSG and 86000PJ in unconventional gas, the latter from Cooper Basin ONLY. Extraction efficiencies have to be applied (ultra conservative number is 10%).
SXY Cooper basin could fuel these powerstations for 48years.
All this confirms my previous calculations that SXY has MASSIVE imbedded value in their gas reserves which are expanding with every hole drilled.
Put 10,000shares away for your grandchildren.
- Forums
- ASX - By Stock
- SXY
- big offloads this morning
big offloads this morning, page-15
-
- There are more pages in this discussion • 11 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add SXY (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
EQN
EQUINOX RESOURCES LIMITED.
Zac Komur, MD & CEO
Zac Komur
MD & CEO
SPONSORED BY The Market Online