    Your response is aligned. Construction is typically a 3 year process all going well. As per any major infrastructure project the runway before and after is as long if not longer hence the ~10 year timeframe. Construction can often be the quickest part. The front end feasibility, approvals, financing and tenders can be quite difficult and elongated.

    • Feasibility Study/Design
    • Approvals - Land, Easements, Water
    • Market Engagement - Commercial model, financing, Tender
    • Tender Award
    • Mobilisation - recruitment, sub contracts etc
    • Procurement
    • Construction - 3 years
    • Commissioning
    • Handover
    • Operations
 