It's been 76 days since the 1st so: 76 days x 32m/day = 2,432m/rig or 4,864m total... divide by 800m/hole = ~6 holes (assuming no breakdowns etc...)
Thinking further downstream we'd then have logging, core processing and sampling (~2wks/hole) then dispatch from site to a lab for assay (~4 weeks/hole) so one 800m hole would take 3.5 weeks to drill + 6 week turn around time or 9.5 weeks at best from start to finish...
- Forums
- ASX - By Stock
- HCH
- $?Bill in a ? Life mine
$?Bill in a ? Life mine, page-5598
-
-
- There are more pages in this discussion • 22,289 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add HCH (ASX) to my watchlist
(20min delay)
|
|||||
Last
77.5¢ |
Change
-0.010(1.27%) |
Mkt cap ! $118.8M |
Open | High | Low | Value | Volume |
78.5¢ | 78.5¢ | 75.0¢ | $105.1K | 138.0K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 15210 | 77.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
78.5¢ | 6917 | 5 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 15210 | 0.775 |
1 | 2450 | 0.765 |
2 | 890 | 0.760 |
1 | 2450 | 0.755 |
4 | 21094 | 0.750 |
Price($) | Vol. | No. |
---|---|---|
0.785 | 6917 | 5 |
0.790 | 1380 | 3 |
0.795 | 24900 | 2 |
0.800 | 8500 | 1 |
0.805 | 2450 | 1 |
Last trade - 14.48pm 18/09/2024 (20 minute delay) ? |
Featured News
HCH (ASX) Chart |