Here is a legal review on this case and potential outcomes....

  1. 476 Posts.
    lightbulb Created with Sketch. 86
    Here is a legal review on this case and potential outcomes. While this is not something anyone should bet on, it is an interesting point of view to consider.

    Predicting the likely outcome of the arbitration case between Cameroon and Sundance Resources at the International Chamber of Commerce (ICC) in Paris, as detailed in the
    Africa Intelligence article from March 26, 2025, involves analyzing similar international arbitration cases involving disputes over mining concessions, government revocation of contracts, and ICC proceedings. While specific outcomes depend on the details of the case (e.g., contract terms, evidence of breach, and applicable law), historical ICC and similar arbitration cases provide a framework for potential scenarios. Below is a likely outcome scenario based on precedent, followed by relevant case examples.
    Likely Outcome Scenario
    Given the dynamics of the Cameroon-Sundance dispute—where Cameroon revoked Sundance Resources’ concession for the Mbalam-Nabeba iron ore project in 2021, leading to arbitration—it’s plausible that the case hinges on whether Cameroon can justify its revocation under the contract and Cameroonian law, versus Sundance’s claim for compensation due to lost investment and potential profits. Historical trends in ICC arbitration suggest a few possible outcomes, with the most likely being a partial award in favor of Sundance Resources, tempered by procedural and jurisdictional nuances:
    1. Partial Compensation for Sundance: The tribunal may find that Cameroon’s revocation breached the contract or failed to follow due process (e.g., insufficient notice or compensation), awarding Sundance damages for sunk costs and a portion of lost profits. However, the award could be reduced if Sundance is found to have contributed to the project’s delays or failed to meet obligations.
    2. Influence of Government Strategy: Ferdinand Ngoh Ngoh’s insistence on pursuing arbitration rather than settling (overriding Laurent Esso’s negotiation attempt) suggests Cameroon believes it has a strong legal defense. If the tribunal accepts Cameroon’s argument (e.g., Sundance’s non-performance), the award could favor Cameroon, limiting or denying compensation.
    3. Settlement Pressure: Despite Ngoh Ngoh’s stance, ICC proceedings often encourage settlement. If evidence weakens Cameroon’s position during hearings, a negotiated settlement mid-arbitration remains possible, potentially lower than Sundance’s initial claim but avoiding a full loss.
    Based on ICC trends and similar cases, the most probable outcome is a compromise: Sundance receives compensation (e.g., $50-150 million, reflecting investment costs and partial lost opportunity), but not the full amount it might seek (potentially hundreds of millions), due to shared fault or jurisdictional limits. Cameroon’s sovereignty argument and Sundance’s performance record will be key factors.
    Precedent Cases and Analysis
    Here are relevant cases that inform this scenario, with citations where available:
    1. Sundance Resources v. Republic of Congo (Precedent Within the Same Company)
      • Background: Sundance Resources faced a similar issue with the Republic of Congo, which withdrew its Nabeba permit in 2020, prompting a separate arbitration claim worth $8.76 billion AUD (approximately $6 billion USD at the time). This case, while not ICC-based, reflects Sundance’s experience with concession disputes in the region.
      • Outcome: As of March 2025, this case remains unresolved publicly, but Sundance’s aggressive claim suggests it will push for substantial damages in the Cameroon case too. However, the Congo case’s high claim was met with skepticism, hinting that tribunals may scale down awards based on realistic loss assessments.
      • Relevance: Indicates Sundance’s strategy and the challenges of proving massive future profits in mining disputes.
    2. Occidental Petroleum Corporation v. Republic of Ecuador (ICSID Case No. ARB/06/11)
      • Background: Ecuador terminated Occidental’s oil concession in 2006, alleging contractual breaches. Occidental sought $3.4 billion in damages via ICSID arbitration.
      • Outcome: In 2012, the tribunal awarded Occidental $1.77 billion (later reduced to $1 billion after annulment proceedings), finding Ecuador’s termination unlawful but reducing damages due to Occidental’s partial fault.
      • Citation: ICSID Case No. ARB/06/11, Award, October 5, 2012.
      • Relevance: Like Cameroon, Ecuador acted unilaterally, but the tribunal balanced state rights with investor losses, suggesting a partial award is plausible for Sundance if Cameroon’s revocation lacks legal grounding.
    3. Crystallex International Corporation v. Bolivarian Republic of Venezuela (ICSID Case No. ARB(AF)/11/2)
      • Background: Venezuela revoked Crystallex’s gold mining permit in 2008 after years of delays, leading to an ICSID claim for $3.16 billion.
      • Outcome: In 2016, the tribunal awarded Crystallex $1.2 billion, finding Venezuela’s actions expropriatory but adjusting damages based on project uncertainties.
      • Citation: ICSID Case No. ARB(AF)/11/2, Award, April 4, 2016.
      • Relevance: Mirrors Cameroon’s revocation of a mining concession; the reduced award reflects tribunals’ caution with speculative profits, applicable to Sundance’s iron ore case.
    4. ICC Case Example: Construction Dispute (Confidential, ICC Case No. 12947, 2005)
      • Background: A Middle Eastern state entity terminated a contractor’s agreement, citing delays. The contractor sought damages for investment and lost profits in an ICC arbitration.
      • Outcome: The tribunal awarded partial compensation for sunk costs but denied lost profits, finding mutual fault. Extracts published in ICC Dispute Resolution Bulletin (2007).
      • Relevance: ICC’s tendency to split responsibility could apply if Sundance and Cameroon both faltered in Mbalam-Nabeba’s development.
    5. Tethyan Copper Company v. Pakistan (ICSID Case No. ARB/12/1)
      • Background: Pakistan rejected Tethyan’s mining license application in 2011, leading to a $11 billion claim.
      • Outcome: In 2019, the tribunal awarded $5.8 billion, later settled for $1 billion in 2022 after negotiations, reflecting Pakistan’s breach but adjusting for feasibility.
      • Citation: ICSID Case No. ARB/12/1, Award, July 12, 2019.
      • Relevance: Shows a high initial award reduced through practical considerations, a potential trajectory if Cameroon loses but negotiates post-award.
    Synthesis and Conclusion
    The Cameroon-Sundance case aligns with patterns in these precedents: a state revoking a resource concession, an investor claiming significant damages, and tribunals often finding a middle ground. ICC arbitration, per its 2023 statistics (890 cases, average dispute $65 million, median $5.5 million), tends to handle complex commercial disputes efficiently, with awards reflecting evidence over ambition. If Cameroon proves Sundance’s non-compliance (e.g., missing deadlines), it could limit damages, as in Occidental. If Sundance demonstrates unjust expropriation, a Crystallex-style award is possible, though tempered by project stage and ICC’s conservative approach to lost profits.
    Thus, a likely outcome is Sundance receiving $50-150 million—covering investments and partial opportunity loss—unless Cameroon’s defense collapses, risking a higher award, or prevails entirely, leaving Sundance empty-handed. Settlement remains a wildcard, especially given Esso’s earlier inclination, though Ngoh Ngoh’s stance complicates this. The tribunal’s decision, expected post-March 2025, will pivot on contract specifics and performance evidence, neither fully detailed in the article but critical to the final ruling.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.