Hi Rocket, I disagree that mine gate costs should be doubled. Mine gate costs are mostly fixed costs, not variable. For example, the majority of the mine gate (production costs) are labour and equipment. Mining costs are probably paid for on a per bcm basis, but there will also be standby costs etc so ultimately, regardless of the material being moved, the contractor will be earning a relatively fixed amount.
So I am predicting that the mine gate costs will flatten out at about $8m per month. If production volumes increases then the unit cost (per dmtu produced) will decrease, but the total expenditure will be flat.
This is the opposite to the logistics cost which are (almost) all purely variable and therefore all paid for on a per tonne hauled or shipped basis.
- Forums
- ASX - By Stock
- E25
- Cashflow prediction quarter
E25
element 25 limited
Add to My Watchlist
0.00%
!
22.5¢

Cashflow prediction quarter, page-45
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
22.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $51.43M |
Open | High | Low | Value | Volume |
22.5¢ | 22.5¢ | 21.5¢ | $21.94K | 100.7K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 2779 | 21.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
22.5¢ | 62609 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 2779 | 0.215 |
2 | 5119 | 0.210 |
2 | 8107 | 0.205 |
7 | 59405 | 0.200 |
3 | 13077 | 0.195 |
Price($) | Vol. | No. |
---|---|---|
0.225 | 62609 | 2 |
0.230 | 72958 | 1 |
0.235 | 24800 | 2 |
0.240 | 252084 | 2 |
0.245 | 21276 | 1 |
Last trade - 16.10pm 27/06/2025 (20 minute delay) ? |
Featured News
E25 (ASX) Chart |
The Watchlist
PAR
PARADIGM BIOPHARMACEUTICALS LIMITED..
Paul Rennie, MD & Founder
Paul Rennie
MD & Founder
SPONSORED BY The Market Online