unfortunately you cant just drill a well, have oil flow to surface and start counting your cash.
a series of wells designed to most productively tap the resivior are required
each well must be drilled and then all infrastructure like production trees and pipelines laid.
oil must be processed
worley parsons has done a very basic field development design,
I believe estimated cost would be in the range of 150-200m (happy to be corrected on this)
so do they have enough info from this well to drill a new well which, if it flows, could be suspended as a future production well
OR
do you keep trying here having blown 15-20m since the first blockage and risk blowing the same again with no more data to show other than a very red bank balance?
- Forums
- ASX - By Stock
- JKA
- chances of news today
chances of news today, page-28
-
- There are more pages in this discussion • 13 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add JKA (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
JBY
JAMES BAY MINERALS LIMITED
Andrew Dornan, Executive Director
Andrew Dornan
Executive Director
Previous Video
Next Video
SPONSORED BY The Market Online