    'The timeframe for completion of project
    financing will follow finalisation of plant design, costing and scheduling '

    In my experience, having been involved in civil/structural design projects, this could take up to 6 months.
    The first stage is a concept/preliminary design, which has to be approvaed by the client - maybe 2 months.
    Then final detailed design and documentation, followed by seeking bids, awarding contract etc - another 4 months.
    Thats all assuming there are no design changes or other delays along the way.
 
watchlist Created with Sketch. Add VYS (ASX) to my watchlist
(20min delay)
Last
49.0¢
Change
-0.010(2.00%)
Mkt cap ! $253.5M
Open High Low Value Volume
50.0¢ 50.5¢ 49.0¢ $168.3K 339.4K

Buyers (Bids)

No. Vol. Price($)
10 175113 48.5¢
 

Sellers (Offers)

Price($) Vol. No.
49.0¢ 20700 1
View Market Depth
Last trade - 13.35pm 11/10/2024 (20 minute delay) ?
VYS (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.