    'The timeframe for completion of project
    financing will follow finalisation of plant design, costing and scheduling '

    In my experience, having been involved in civil/structural design projects, this could take up to 6 months.
    The first stage is a concept/preliminary design, which has to be approvaed by the client - maybe 2 months.
    Then final detailed design and documentation, followed by seeking bids, awarding contract etc - another 4 months.
    Thats all assuming there are no design changes or other delays along the way.
 
watchlist Created with Sketch. Add VYS (ASX) to my watchlist
(20min delay)
Last
46.0¢
Change
0.015(3.37%)
Mkt cap ! $194.0M
Open High Low Value Volume
45.0¢ 46.5¢ 44.5¢ $580.6K 1.274M

Buyers (Bids)

No. Vol. Price($)
3 11672 45.5¢
 

Sellers (Offers)

Price($) Vol. No.
46.5¢ 16173 1
View Market Depth
Last trade - 16.10pm 06/09/2024 (20 minute delay) ?
VYS (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.