ETR 0.00% 0.7¢ entyr limited

clarification from management re ann., page-11

  1. 7,372 Posts.
    lightbulb Created with Sketch. 1331
    The Operator plans to run a
    second intermediary casing string once the well is drilled down to approximately 3,200 ft, setting the second
    casing string above the primary C18 and C19 carbonate reservoirs.

    From the Feb 20 update

    Oilman will this casing be cemented into place like the first casing, if so then drilling would stop for a few days to a week,this would be a good time to test and report c13 through to c17.

    Would like your thoughts, cheers.
 
watchlist Created with Sketch. Add ETR (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.