    Goldstar commissions ore haulage system at Eureka
    10:21, Wednesday, 10 January 2007

    Sydney - Wednesday - Jan 10: (RWE Australian Business News) -
    Goldstar Resources NL (ASX: GDR) reports the Skipway haulage system at
    the Eureka project, 2km east of Walhalla in Victoria, has been
    successfully commissioned, to meet the first ore haulage requirements of
    the Eureka Bulk Sampling Program (EBSP).
    Following the bushfire crisis in the East Gippsland region over
    the Christmas period, Goldstar personnel regained access to both the
    Eureka and Tubal Cain sites on December 27.
    When unrestricted access was re-established, site personnel
    returned all relocatable equipment to site, confirmed all cables were
    electrically intact and re-powered the site on December 28.
    Construction and commissioning work on the Skipway continued
    with the installation of the winder in the first week of the New Year.
    Final commissioning of the Skipway system was completed
    yesterday. All aspects of the Skipway haulage system are now operating
    according to design specification and ready to accommodate the full ore
    haulage requirements of the EBSP.
    The underground mining crew resumed operations at Eureka on
    December 29, initially on day-shift only, before resuming full two-shift
    operations on January 2.

    *****

    Stripping and widening of the old Western Adit to establish
    mining access as part of the EBSP has to date progressed 96 metres.
    To recover some of the time lost due to the fires and improve
    ore accessibility, the decision has been taken to cross-cut to ore at an
    earlier position along the Western Adit.
    The mining face is currently estimated to be 50 metres from the
    first of the potentially high-grade reefs of the Eureka Dyke Bulge.
    Upon intersection of the reefs strike driving will commence to
    collect samples for grade continuity and metallurgical assessment.
    Based on the current rate of advance, Goldstar expects to
    intersect the first quartz reefs and commence extraction of initial bulk
    samples of high-grade quartz reef material during January.
    As part of the EBSP, Goldstar is aiming to access between four
    and six of the total package of nine high-grade quartz reefs identified
    within the Eureka Dyke Bulge.

 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.