Gday sevie and apologies for the legth of the reply:
"BOLNISI GOLD NL 2002-07-30 ASX-SIGNAL-G
HOMEX - Sydney
+++++++++++++++++++++++++
QUARTERLY HIGHLIGHTS
1. QUARTZITE PROJECT
* Quarterly gold production continues to increase up to 24,472
ounces.
* Cash operating costs reduced to US$150 per ounce for the quarter.
* Heap leach quarterly stacked tonnage was 470,262 tonnes at 2.29 g/t
Au head grade.
* US$1.5 million cash flow surplus repatriated to the Company in
Australia.
OCAMPO PROJECT
* Feasibility study program commenced and on schedule.
* Ocampo Project drilling commenced for resource confirmation and
metallurgical samples.
* Positive initial assay results from resource confirmation
drillholes.
* Excellent preliminary metallurgical recoveries of approximately 95%
Au and 83% Ag.
ROSEBY PROJECT
* Roseby Project drilling commenced for resource confirmation and
metallurgical samples.
* Positive preliminary drilling results received for the Roseby
Project.
* Positive preliminary metallurgical testwork results received for
the Roseby Project.
2. GEORGIAN OPERATIONS
Bolnisi Gold NL ("the Company") has been active in the Bolnisi Region
of Georgia since 1993 through its subsidiaries Quartzite Ltd which
has been producing gold since April 1997, and Trans Georgian
Resources Ltd which holds an exploration licence in southern Georgia
containing occurrences of volcanically hosted gold and massive
sulphide mineralisation.
2.1 QUARTZITE LTD ('QUARTZITE')
QUARTZITE PROJECT (BOLNISI 50%)
SUMMARY
Since April 1997, Quartzite has been recovering gold and silver by
heap leach methods from an indicated resource of 12,000,000 tonnes of
auriferous siliceous ore averaging 1A g/t Au, stockpiled at the
Madneuli Mine near Kazreti in the former Soviet Republic of Georgia.
Quartzite Project gold production and heap leach performance
continued to improve during the June 2002 quarter. Gold production
increased to 24,472 ounces at a cash cost of US$150 per ounce.
Gold dore produced by the Quartzite Project continues to be shipped
to Johnson Matthey in the United Kingdom for refining and sale.
Surplus funds generated by the Quartzite Project are distributed to
the partners in the project. During the June 2002 quarter,
US$1,500,000 was distributed to the Company and the funds were
repatriated to Australia.
QUARTZITE PROJECT PRODUCTION INFORMATION
A summary of the Quartzite Project production to 30 June 2002 is as
follows:
QUARTER PROJECT TO DATE
1 APRIL 2002 1 MAY 1997
TO TO
30 JUNE 2002 30 JUNE 2002
Ore processed (tonnes) 470,262 6,226,940
Gold produced (oz) 24,472 263,555
Silver produced (oz) 10,695 118,439
Head grade (g/t AU) 2.29 2.31
Recovered grade (g/t Au) 1.62 1.32
Cash operating costs 3,662 43,587
(US$'000)
Cash operating cost
per ounce (US$) 150 165
The following points should be noted in relation to the above
Quartzite Project production summary:
* Gold produced during the June quarter represents an 11% increase on
the previous quarter's production.
* The cash operating cost per ounce for the June quarter has been
maintained at a low US$150 per ounce.
* Gold recoveries during the June quarter were approximately 94% of
the gold loaded onto the heaps, reflecting a near equilibrium status
of the heaps during the quarter.
* Ore on the heap leach pad is estimated to contain a total of
approximately 83,000 ounces of gold which will be recovered by the
heap leach process with minimal additional operating costs.
As reflected in the graph of historic Quartzite Project production
information below, gold production levels and cash operating costs
per ounce of gold produced have been stabilised at the current highly
profitable levels.
2.2 TRANS GEORGIAN RESOURCES LTD ('TGR')
GOLD AND BASE METALS PROJECTS (BOLNISI 50%)
April 2002 was the third anniversary of the 5 year renewal of Licence
9, the 'exploration licence', and further reduction in area was both
required under the terms of the licence and planned by the Company.
TGR has retained a total of 48.65 sq. km of the area renewed in April
1999 in two areas. Firstly, 47 sq. km in the Sakdrisi-Darbazi area NW
of Madneuli/Kazreti protecting areas of known potential 'quartzite'
gold and copper mineralisation, and secondly, 1.65 sq. km adjoining
the eastern margin of the Madneuli mine lease covering a possible
extension of the Eastern Quartzite body which outcrops within the
Madneuli pit. Both these areas are seen as potential future sources
of ore to supply the Quartzite and Madneuli operations.
Licence 10, the original 'advanced' properties licence, reached the
end of its geological exploration term in April 2002 and entered its
'development' phase. Of the original 5 properties, Sakdrisi,
Dambludka, Tsiteli Sopeli, Kvemo Bolnisi, and David Garedji, only
Sakdrisi was deemed to be of sufficient potential to be considered
for further evaluation. Sakdrisi hosts both gold bearing secondary
quartzite mineralisation and, at depth, copper sulphides which may
have potential as future sources of ore to both the Quartzite and
Madneuli operations.
The retained Sakdrisi property of Licence 10 lies within the retained
portion of the exploration licence.
3. OCAMPO GOLD-SILVER PROJECT (BOLNISI EARNING 60%)
The Ocampo Project, located in the Sierra Madre Occidental
metallogenic province, Chihuahua, Mexico covers 3,499 hectares. The
Company has the right to earn a 60% interest in a defined area within
the Ocampo Project and the gold and silver resources contained
therein. The area of interest covered by the Company's agreement
contains the majority of the already defined existing open pittable
oxide resources and, in the Company's opinion, the majority of any
potential for further upside.
3.1 DRILLING PROGRAM
At Ocampo, gold/silver mineralisation is of the intrusion-related low
sulphidation epithermal style with ore deposition controlled in
structural settings locally referred to as clavos (ore shoots).
The objective of the current drill program, as part of the Ocampo
Project feasibility study, is to develop the resource model to
Australian JORC standards enabling ore reserves to be determined, pit
outlines defined and mining schedules detailed thus facilitating
completion of feasibility and subsequent development. In parallel,
this program has provided core samples for metallurgical,
geotechnical, geological and environmental purposes.
A total of 4,486 metres of diamond core and reverse circulation (RC)
drilling has been completed on the Ocampo Project over the last
quarter. This included the drilling of twelve 61.5mm diameter HQ core
holes for sample for metallurgical testwork, along with 29 RC
drillholes designed to infill and extend the existing drill pattern
at Plaza de Gallos, Refugio and the eastern end of Conico. Assay
results are awaited on drillhole ODH-268 to ODH-279. When these
assays are to hand, the resource model will be updated (a continuing
process) and the next phase of drilling will proceed. This is
estimated to entail a further 4,400 metres of RC drilling in 25 holes
to complete Plaza de Gallos and Refugio, and 3,500 metres at Picacho.
Progress during this current program has been made in increasing
understanding of ore controls. It is now considered that dip
continuity of ore shoots is not as important as the plunge control of
those shoots and alteration control is also better understood. On the
upside, grade and continuity is holding up down plunge.
Overall, pending further assays and resource modelling, the measured
category of resources appears to have been increased and there is
better continuity and control over early mining resources in Plaza de
Gallos and Refugio.
METALLURGICAL DRILLING
The 12 metallurgical drillholes twinned existing holes which were
considered representative of the mineralisation. Four holes were
collared at both Plaza de Gallos and Refugio and two each at Picacho
and Conico. Drillholes ODH-242 and 243 were terminated in old
workings not intersected in the original holes ODH-79 and 72.
Drillholes ODH-252 and 253 were both drilled as twins of ODH-1. This
core has been shipped to an Australian metallurgical laboratory for
carbon in leach testwork, crushing, grinding, compressive strength
tests, and general process testwork which will assist in determining
the optimum process route for Ocampo ore.
RESOURCE/RESERVE DRILLING
PLAZA DE GALLOS
At Plaza de Gallos, drilling resulted in the following significant
results:
DRILLHOLE AREA FROM TO INTERCEPT Au g/t Ag g/t
(m)
ODH-242 PDG 126.5 134.1 7.6 3.39 52
ODH-261 PDG 7.0 29.9 22.9 6.75 45
34.4 48.2 13.7 2.44 46
ODH-262 PDG 5.5 54.3 48.8 2.48 33
ODH-266 PDG 36.0 39.0 3.0 2.58 92
46.6 48.2 1.5 5.39 48
Infill drilling was completed on the two western sections of Plaza de
Gallos. Assay results are awaited but a preliminary geological
interpretation suggests that the drilling has tracked the north-west
plunge of the Plaza de Gallos mineralisation in between previous
drill intercepts on these sections.
REFUGIO
At Refugio, drillholes ODH-240, 245, 263, 264, 265 and 272 were
drilled to test the up-dip continuity of the mineralisation and to
ensure adequate control on grade interpolation in the near surface
zone. Drill results are encouraging with quartz breccia and
stockworking being intersected in all holes along with some
significant mineralised intercepts as follows:
DRILLHOLE AREA FROM TO INTERCEPT Au g/t Ag g/t
(m)
ODH-245 REF 1.5 19.8 18.3 1.54 93
ODH-263 REF 0.0 13.1 13.1 2.10 100
ODH-264 REF 12.8 28.0 15.2 1.24 74
ODH-265 REF 8.5 34.4 25.9 0.96 57
3.2 METALLURGY
Gravity leach tests were performed on RC chip composite samples from
the earlier drilling campaign at Refugio (drillholes ODH-091 and
118). Agitated leach tests at a grind size of 80% passing 75 microns
were completed with and without gravity separation prior to leaching.
The samples leached very well with about 95% of the gold extracted
after 24 hours of leaching with and without the gravity step. The
latter improved the silver leaching rate and therefore the silver
extraction after 24 hours by an average of approximately 6% for the
two composites tested giving an average silver recovery of about 83%.
This test work was repeated at a grind size of 80% passing 53
microns. For the lower grade composite (ODH118) there is a slight
improvement in both gold and silver recoveries indicated by grinding
to a p80 = 53 microns compared with a p80 = 75 microns for a leaching
time of 24 and 48 hours. This equates to about US$0.08 per tonne but
additional power costs for the finer grind is about 3 times this
value.
There was a slight improvement in the gold recovery for the higher
grade composite (ODH091) after 24 hours of leaching but not enough to
cover the additional power cost of the finer grind. Silver recovery
after 24 hours was actually lower at the finer grind size. After 48
hours of leaching, the additional gold and silver recovery at the p80
= 53 microns is more significant at about US$0.43 per tonne.
Broadly speaking based on these two composite samples there appears
to be no advantage in going to the finer grind. Further tests are in
progress, the bulk of it on the new core samples drilled this
quarter. This work will assist in determining whether heap leach or
conventional crush/grind, leaching and carbon recovery of gold and
silver is the optimum process route for treatment of the Ocampo ore.
3.3 ENGINEERING
New aerial photography at a scale of 1:10000 was flown at the end of
the dry season in mid-June. This photography will enable detailed 1
metre contour topographic plans to be produced to assist in project
design and construction. Photogrammetry will be commenced shortly.
This photography also has geological applications.
Investigations into availability of good quality used processing
equipment in North America are ongoing.
3.4 FUTURE WORK
As noted above, on completion of the review of the results of the
drilling completed to date, the Ocampo Project resource model will be
updated and a further 4,400 metres of RC drilling will be undertaken
at Plaza de Gallos and Refugio and 3,500 metres at Picacho. This
program is intended to enable mine scheduling and pit outlines to be
determined for feasibility and development purposes.
Metallurgical testwork, engineering design work and environmental
studies will be progressed in anticipation of the commencement of
plant construction.
4. ROSEBY JOINT VENTURE
COPPER PROJECT (BOLNISI 50% EARNING UP TO 70%)
Roseby is a significant oxide copper resource north of Cloncurry in
the Mt Isa-Cloncurry field in NW Queensland covered by two joint
ventures, the Feasibility and Exploration Joint Ventures. The Company
holds a 50% interest in two joint ventures and has the right to
increase its share of the Feasibility Joint Venture to 70%. A high
proportion (up to 60%) of the copper occurs as fine-grained native
copper, which may be recoverable by relatively simple and inexpensive
gravity separation methods.
4.1 METALLURGY
During the quarter ended 30 June 2002, preliminary metallurgical
testwork was carried out on core samples which were available from a
drilling program conducted some 10 years ago, to test the Company's
belief that the Roseby Project copper may be recoverable by simple
and inexpensive gravity separation methods.
The highly encouraging results of this testwork were reported in
detail by the Company on 5 June 2002 and are summarised below.
Approximately 50% of the contained copper was recovered by gravity
recovery techniques into a 25% copper concentrate. Total recoveries
after a flotation recovery process, which was adversely affected by
the oxidation of the 10 year old metallurgical core sample, increased
to in excess of 60% recovery into a 20% concentrate.
There is potential to increase the copper recovery, and to
significantly improve the concentrate grade achieved by the
preliminary metallurgical testwork. Gravity recovery of copper could
be improved by reprocessing the initial gravity tailings and by
regrinding and reprocessing of a gravity middlings product. The
gravity concentrate grade could be improved, if necessary, by
regrinding and reprocessing in a cleaner stage. Flotation recoveries
are likely to be increased following reagent optimisation and by
conducting cleaner stages of flotation. Flotation recoveries are also
likely to increase when ore, which has not been subjected to several
years of oxidation, is processed.
4.2 DRILLING
A drilling program, with the principal aims of verifying ore grade
and thickness reported from programs conducted by previous tenement
holders and to provide sample material for a comprehensive
metallurgical testwork program, was commenced in mid June completed
in late July 2002.
A total of 1,084 metres of HQ3 core drilling in 8 holes and 851
metres RC drilling in 6 holes was completed at the Blackard and
Scanlan deposits. Most of the drilling was at the Blackard deposit.
Results for the first four holes have been received. Significant
amounts of generally fine grained native copper were intersected in
most holes. Results to date are highly encouraging and, using a 0.5%
Cu cut-off, are summarised as follows:
HOLE DEPOSIT CO-ORDINATES DIP FROM TO INTER- GRADE A
NO VAL % Cu
EAST NORTH DEG (m) (m) (m)
BC 265 Blackard 412177 7765835 -90 46 96 50 1.03 Native
Copper
104 114 10 1.44 Chalco-
cite
BC 266 Blackard 412319 7765451 -90 38 76 38 1.05 Native
Copper
SC 116 Scanlan 412171 7753866 -90 10 114 104 0.93 Native
Copper
SC 117 Scanlan 412151 7753939 -90 44 180 136 1.87 Native
Copper
A = Dominant Copper Mineralisation
4.3 FUTURE WORK
Further metallurgical testwork is scheduled to be conducted on
samples to be collected from the current drilling program to
facilitate a plant flowsheet design and feasibility study. In
conjunction with this work, further resource definition drilling is
planned together with the collection of environmental data for the
completion of environmental studies.
Both BSG and BSGOA are worth consideration at these prices, but do your own research.
Cheers, Nick
- Forums
- ASX - By Stock
- BSG
- Whats happening ????
BSG
bolnisi gold nl
Whats happening ????, page-2
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)