MZI 0.00% 1.6¢ mzi resources ltd

From the March 25th annoucment:Construction of key mining and...

  1. 1,462 Posts.
    lightbulb Created with Sketch. 35


    From the March 25th annoucment:

    Construction of key mining and processing equipment is now almost complete, with staff and
    equipment set to be mobilised to site next month ahead of the proposed restart of operations in the
    second quarter.

    As part of its 2010 Mine Plan, Matilda has introduced a number of enhanced mining and processing
    methods which will double plant capacity and reduce operating costs. This includes the introduction of
    an in-pit mobile slurry unit, and a pre-concentrator facility.

 
watchlist Created with Sketch. Add MZI (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.