STX 0.00% 22.5¢ strike energy limited

cooking with gas, page-42

  1. 205 Posts.
    lightbulb Created with Sketch. 27
    Dismal progress over the last 3 weeks means they’ve lost all their schedule float. They aren’t even at mechanical completion yet and from the photos on Strike’s latest presentation they still appear to be welding a couple of final bends. One hopes these are old photos, but they were supposed to have finished piping installation some time back. Their apparent reluctance to provide a comprehensive set of close up photos is also a concern. It all raises questions on the accuracy of reported progress.

    They could still get to first gas by the end of Q3 if construction verification has been done properly, Mechanical Completion is genuinely imminent and they had a good commissioning team. Based on the information reported to date, I don’t hold much confidence on any of those points.
 
watchlist Created with Sketch. Add STX (ASX) to my watchlist
(20min delay)
Last
22.5¢
Change
0.000(0.00%)
Mkt cap ! $643.6M
Open High Low Value Volume
22.5¢ 23.3¢ 22.0¢ $2.570M 11.38M

Buyers (Bids)

No. Vol. Price($)
14 1560870 22.0¢
 

Sellers (Offers)

Price($) Vol. No.
22.5¢ 525234 8
View Market Depth
Last trade - 16.10pm 04/07/2024 (20 minute delay) ?
STX (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.