copper production doubles for dec qtr

  1. 197 Posts.
    snippet frpm latest qtrly report released tonight

    1.2 Production December Quarter
    For half of the quarter, production was sourced from an older leach vat established by the previous project owners. A new leach vat was commissioned in mid October followed by a second one in November, bringing the total fresh oxides under leach to 13,000 tonnes of ore, at an estimated head grade of
    5% Cu. Copper production during the quarter almost doubledthe previous quarter to 118 tonnes (63 tonnes in the September quarter). Sales revenue for the quarter was $716,000, excluding GST ($445,000 excluding GST n the September quarter).
 